Test Showing. Each SCT must demonstrate that the Facility: (1) successfully started; (2) operated for at least [four (4)] consecutive hours at Maximum Discharging Capacity; (3) operated for at least [four (4)] consecutive hours at Maximum Charging Capacity; (4) has a Storage Capacity of an amount that is, at least, equal to the Maximum Stored Energy Level (as defined in Exhibit O); and (5) is able to deliver Discharging Energy to the Delivery Point as measured by the Facility Meter for [four (4)] consecutive hours at a rate equal to the Maximum Discharging Capacity.
Appears in 1 contract
Sources: Energy Storage Agreement
Test Showing. Each SCT must demonstrate that the Facility:
(1) successfully started;
(2) operated for at least [four (4)] ) consecutive hours at Maximum Discharging Capacity;
(3) operated for at least [four (4)] ) consecutive hours at Maximum Charging Capacity;
(4) has a Storage Capacity of an amount that is, at least, equal to the Maximum Stored Energy Level (as defined in Exhibit OA); and
(5) is able to deliver Discharging Energy to the Delivery Point as measured by the Facility Meter for [four (4)] ) consecutive hours at a rate equal to the Maximum Discharging Capacity.