Test Window. The Capacity Test must be performed within thirty (30) days of Substantial Completion unless extended due to weather or equipment malfunction as follows. If the test is not able to be completed due to weather, the time frame for performing the test shall be extended until the minimum data collection requirements of ASTM E2848-13 have been met. If the test is not able to be completed due to malfunction of equipment installed under this Agreement, the time frame for performing the test shall be extended to thirty (30) days after repairs to said equipment are complete.