TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO shall test the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each
Appears in 13 contracts
Sources: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO shall test the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. EachInterconnection
Appears in 10 contracts
Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO shall test the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Eachthe
Appears in 4 contracts
Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement
TESTING AND INSPECTION. 6.1 6.1. Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO Transmission Provider shall test the Participating TO’s Transmission Provider's Interconnection Facilities, Network Upgrades, and or Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s 's Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Eachinitial
Appears in 3 contracts
Sources: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO Transmission Provider shall test the Participating TO’s Transmission Provider's Interconnection Facilities, Facilities and Network Upgrades, and Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s 's Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each.
Appears in 3 contracts
Sources: Surplus Large Generator Interconnection Agreement, Agreement to Amend Surplus Large Generator Interconnection Agreement, Agreement to Amend Surplus Large Generator Interconnection Agreement
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO shall test the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each,
Appears in 3 contracts
Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement
TESTING AND INSPECTION.
6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO shall test the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each
Appears in 3 contracts
Sources: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO shall test the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Eachthe
Appears in 3 contracts
Sources: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement (Lgia)
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO shall test the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Eachand
Appears in 2 contracts
Sources: Large Generator Interconnection Agreement (Lgia), Large Generator Interconnection Agreement (Lgia)
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO Transmission Provider shall test the Participating TO’s Transmission Provider's Interconnection Facilities, Facilities and Network Upgrades, and Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s 's Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Eachensure
Appears in 2 contracts
Sources: Qualifying Facility Large Generator Interconnection Agreement, Qualifying Facility Large Generator Interconnection Agreement
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO Transmission Owner shall test the Participating TOTransmission Owner’s Interconnection Facilities, Network Upgrades, Transmission Owner’s System Protection Facilities and Distribution Upgrades Upgrades, and the Interconnection Customer shall test each electric production device at the Large Generating Facility Facility, Interconnection Customer’s System Protection Facilities, including control equipment to limit injection at the POI to the level of Interconnection Service set forth in Appendix A and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Each’s
Appears in 2 contracts
Sources: Generator Interconnection Agreement, Generator Interconnection Agreement
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO Transmission Owner shall test the Participating TOTransmission Owner’s Interconnection Facilities, Network Upgrades, Transmission Owner’s System Protection Facilities and Distribution Upgrades Upgrades, and the Interconnection Customer shall test each electric production device at the Large Generating Facility and the Facility, Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. EachSystem
Appears in 1 contract
Sources: Generator Interconnection Agreement
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO Interconnecting Transmission Owner shall test the Participating TOInterconnecting Transmission Owner’s Interconnection Facilities, Facilities and Network Upgrades, and Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. EachEach Party shall make any modifications to its facilities that are found to be necessary as a result
Appears in 1 contract
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO Transmission Owner shall test the Participating TOTransmission Owner’s Interconnection Facilities, Network Upgrades, Transmission Owner’s System Protection Facilities and Distribution Upgrades Upgrades, and the Interconnection Customer shall test each electric production device at the Large Generating Facility Facility, Interconnection Customer’s System Protection Facilities and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Eachto
Appears in 1 contract
Sources: Generator Interconnection Agreement
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO shall test the Participating TO’s Interconnection Facilities, Network Upgrades, and Distribution Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. EachEach Party shall make any modifications to its facilities that are found to be necessary
Appears in 1 contract
TESTING AND INSPECTION. 6.1 Pre-Commercial Operation Date Testing and Modifications. Prior to the Commercial Operation Date, the Participating TO Distribution Provider shall test the Participating TO’s Distribution Provider's Interconnection Facilities, Network Distribution Upgrades, and Distribution Network Upgrades and the Interconnection Customer shall test the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. EachEach Party shall make any modifications to its facilities that are found
Appears in 1 contract