Testing of Interconnection Facilities. In addition to the respective obligations set out under this Clause 6, the Parties shall use all reasonable endeavours to cooperate in testing the Interconnection Facilities in accordance with Schedule 2 - and the schedule developed by the Operating Committee (but in no event later than the time provided in Clause Error! Reference source not found.) and at such other times thereafter as either Party may reasonably require. Each Party shall bear its own costs in connection with any such testing.