Testing Period. (a) When the construction of the Regional MSW Facility has been substantially completed the Concessionaire shall so notify the Project Engineer in writing. Thereafter, the Project Engineer shall, within (7) seven days of the receipt of such notice, cause the Regional MSW Facility to be inspected. (b) Once the Project Engineer has inspected the Regional MSW Facility, the Project Engineer shall issue a Partial Readiness Certificate and the Testing Period of the Regional MSW Facility shall commence from the date of issuance of Partial Readiness Certificate. (c) During the Testing Period, which is a period of maximum of three (3) months, the Project Engineer shall inspect Regional MSW Facility in presence of the representatives of the Concessionaire so as to ascertain any material defects, imperfections, shortcomings or such other faults. During this Testing Period, the Project Engineer may also require any trial runs and/or performance tests under his supervision. (d) The Project Engineer on being satisfied that (i) all the works stipulated in sub-clause 11.2 above have been completed; (ii) there are no defects which need remedied; and (iii) the Regional MSW Facility can be used and operated for the treatment and disposal of MSW, the Project Engineer shall issue a Readiness Certificate. (e) If any latent defect or other defect not in the nature of a defect specified in subsection (c) above appears in the Project during the Term, the Concessionaire shall undertake to make any repairs or take any remedial measures that are reasonably required to remedy any such defect. Such repairs or remedial measures shall be taken up as part of the Operations and Maintenance of the Project under this Agreement. (f) For the purposes of conducting trial runs and performance tests as provided under Clause 11.4, the Grantor ULB and Participating ULBs at their own cost and expense shall provide a Testing MSW Quantity to the Concessionaire after the Concessionaire submits a written request to the Project Engineer in relation to such Testing Quantity.
Appears in 1 contract
Sources: Project Implementation Agreement
Testing Period. (a) When the construction of the Regional MSW Facility Facility, has been substantially completed (including the construction of the Plant has been fully completed) the Concessionaire shall so notify the Project Engineer in writing. Thereafter, the Project Engineer shall, within (7) seven days of the receipt of such notice, cause the Regional MSW Facility to be inspected.
(b) Once the Project Engineer has inspected the Regional MSW Facility, the Project Engineer shall issue a Partial Readiness Certificate and the Testing Period of the Regional MSW Facility shall commence from the date of issuance of Partial Readiness Certificate.
(c) During the Testing Period, which is a period of maximum of three (3) months, the Project Engineer shall inspect Regional MSW Facility in presence of the representatives of the Concessionaire so as to ascertain any material defects, imperfections, shortcomings or such other faults. During this Testing Period, the Project Engineer may also require and supervise any trial runs and/or performance tests under his supervision.
(d) The Project Engineer on being satisfied that (i) all the works stipulated in sub-clause 11.2 (c) above have been completed; (ii) there are no defects which need remedied; and (iii) the Regional MSW Facility can be used and operated for the treatment and disposal of MSW, the Project Engineer shall issue a Readiness Certificate.
(e) If any latent defect or other defect not in the nature of a defect specified in subsection (c) above appears in the Project during the Term, the Concessionaire shall undertake to make any repairs or take any remedial measures that are reasonably required to remedy any such defect. Such repairs or remedial measures shall be taken up as part of the Operations and Maintenance of the Project under this Agreement.
(f) For the purposes of conducting trial runs and performance tests as provided under Clause 11.4, the Grantor ULB and Participating ULBs at their its own cost and expense shall provide a Testing MSW Quantity to the Concessionaire after the Concessionaire submits a written request to the Project Engineer in relation to such Testing Quantity.
Appears in 1 contract
Sources: Project Implementation Agreement