Testing Period. (a) As from [date determined by the Parties], the Producer shall be entitled to inject Power into the network provided that the following conditions precedent are fulfilled (the Testing Period): (i) all conditions precedent to the first utilisation of the Facilities Agreement have been fulfilled or waived as confirmed by a statement provided by the Lenders; (ii) the Wind Farm has been attached to the Balancing Group by way of designation by the Producer of the entity designated as Balance Responsible Entity by the Buyer; (iii) the Producer has notified the Buyer in writing at least [five (5)] Business Days prior to such date of the beginning of the Testing Period. (b) The Testing Period shall be automatically terminated on the Supply Period Commencement Date, in accordance with the provisions of Clause 2.3 below.