Common use of Tests Upon and After Synchronization of the Complex and Commissioning Tests Clause in Contracts

Tests Upon and After Synchronization of the Complex and Commissioning Tests. (a) After first synchronizing the Complex, initial operational testing of the Complex shall be conducted by the Company or its Contractors. Once the Company is satisfied that the Complex is capable of continued reliable operation, the Company shall request the Engineer to issue the Certificate of Readiness. Upon the issuance by the Engineer of the Certificate of Readiness, the Company shall so notify the Power Purchaser and carry out or cause its Contractors to carry out, the following tests (the “Commissioning Tests”), which if the Complex satisfies the minimum performance criteria therefor, will result in the Complex being Commissioned and in the establishment of the Commercial Operations Date in accordance with Section 8.3(c)(iii): (i) initial Tested Capacity test; (ii) reliability run test; (iii) automatic voltage regulator operation test; (iv) boiler/turbine governor operation (droop) test; (v) reactive capability; (vi) minimum load capability; (vii) response of Complex to step load changes; and (viii) full load rejection. Minimum performance criteria for the Commissioning Tests are included in Schedule 7. (b) Reliability Run and Initial Tested Capacity. Upon completion of the reliability run test prerequisites as included in Schedule 7, the Company shall declare to the Power Purchaser the commencement of the reliability run test. During the one hundred and sixty- eight (168) hour period of the reliability run test, the initial Tested Capacity of the Complex will be determined in the following manner: (i) The Complex shall be in operation at full output with normal auxiliaries and full colony load, if connected directly to the Complex, in service. (ii) The Company will declare to the Power Purchaser the commencement of the test and will record the reading of the Metering System. (iii) The test duration will be six (6) continuous hours and at the end of this period the Company will record the new reading of the Metering System. The initial Tested Capacity as determined by such test shall be the difference between the reading taken at the end of the six (6) hour period and the reading taken at the beginning of such period, divided by six (6) and such result adjusted to Reference Conditions; provided, that , subject to Section 2.9(b), the initial Tested Capacity shall not be considered to have been established unless the result of such determination is equal to or greater than the Contract Capacity and satisfies the minimum criteria for such test set forth in Schedule 7. On the completion of the Commissioning Tests, the initial Tested Capacity (adjusted to Reference Conditions) shall be certified by the Engineer (the “Capacity Test Certificate”).

Appears in 1 contract

Sources: Power Purchase Agreement

Tests Upon and After Synchronization of the Complex and Commissioning Tests. (a) After first synchronizing the Complex, initial operational testing of the Complex shall be conducted by the Company or its Contractors. Once the Company is satisfied that the Complex is capable of continued reliable operation, the Company shall request the Engineer to issue the Certificate of Readiness. Upon the issuance by the Engineer of the Certificate of Readiness, the Company shall so notify the Power Purchaser and NTDC and carry out or cause its Contractors to carry out, the following tests (the “Commissioning Tests”), which if the Complex satisfies the minimum performance criteria therefor, will result in the Complex being Commissioned and in the establishment of the Commercial Operations Date in accordance with Section 8.3(c)(iii): (i) initial Tested Capacity test; (ii) reliability run test; (iii) automatic voltage regulator operation test; (iv) boilerengine/turbine governor operation (droop) test; (v) reactive capability; (vi) minimum load capability; (vii) response of Complex to step load changes; and (viii) full load rejection. Minimum performance criteria for the Commissioning Tests are included in Schedule 7. (b) Reliability Run and Initial Tested Capacity. Upon completion of the reliability run test prerequisites as included in Schedule 7, the Company shall declare to the Power Purchaser and NTDC the commencement of the reliability run testtest including the test under Section 8.3(a)(i). During the one hundred and sixty- sixty-eight (168) hour period of the reliability run test, the initial Tested Capacity of the Complex will be determined in the following manner: (i) The Complex shall be in operation at full output with normal auxiliaries and full colony load, if connected directly to the Complex, in service. (ii) The Company will declare to the Power Purchaser and NTDC the commencement of the test and will record the reading of the Metering System. (iii) The test duration will be six (6) continuous hours and and, at the end of this period period, the Company will record the new reading of the Metering System. The initial Tested Capacity as determined by such test shall be the difference between the reading taken at the end of the six (6) hour period and the reading taken at the beginning of such period, divided by six (6) and such result adjusted to Reference Conditions; provided, that that, subject to Section 2.9(b), the initial Tested Capacity shall not be considered to have been established unless the result of such determination is equal to or greater than the Contract Capacity and satisfies the minimum criteria for such test set forth in Schedule 7. On At the completion of the Commissioning Tests, the initial Tested Capacity (adjusted to Reference Conditions) shall be certified by the Engineer (the “Capacity Test Certificate”).

Appears in 1 contract

Sources: Power Purchase Agreement

Tests Upon and After Synchronization of the Complex and Commissioning Tests. (a) After first synchronizing the Complex, initial operational testing of the Complex shall be conducted by the Company or its ContractorsContractor. Once the Company Contractor is satisfied that the Complex is capable of continued c ontinued reliable operationop eration, the Company shall request C ontractor sh all r equest the Engineer to issue E ngineer t o i ssue the Certificate of ReadinessR eadiness. Upon the issuance by the Engineer E ngineer of the Certificate of t he C ertificate o f Readiness, the Company Contractor shall so notify the Power Purchaser Employer and carry out or cause its Contractors to carry out, the following tests (the “Commissioning Tests”), which if the Complex satisfies the minimum performance criteria therefor, will result in the Complex being Commissioned and in the establishment of the Commercial Operations Date in accordance with Section 8.3(c)(iii9.3(c)(iii): (i) initial Tested Capacity test; (ii) reliability run test; (iii) automatic voltage regulator operation testdroop; (iv) boiler/turbine governor operation (droop) operation, including a steam governor over speed test; (v) reactive capability; (vi) minimum load capability; (vii) response of Complex to step load changes; and (viii) full load rejection. rejection Minimum performance criteria pe rformance c riteria for the t he C ommissioning T ests are i ncluded in The Commissioning Tests are included in Schedule 7and Testing Schedule. (b) Reliability Run and Initial initial Tested Capacity. Upon completion of the reliability run test prerequisites as included in Schedule 7[●], the Company Contractor shall declare de clare to the Power Purchaser the commencement of the t he E mployer t he c ommencement o f t he reliability run testr un test (including t he test u nder Section 9.3(a)(i)). During the one hundred and sixty- eight D uring t he 30 (168thirty) hour day period of the t he reliability run test, the initial Tested Capacity of the Complex will be determined in the following manner: (i) The Complex shall be in operation at full output with normal auxiliaries and full colony load, if connected directly to the Complex, in service. (ii) The Company Contractor will declare to the Power Purchaser Employer the commencement of the test and will record the reading of the Metering System. (iii) The test duration will be six (6) continuous hours and at the end of this period the Company Contractor will record the new reading of the Metering System. The initial Tested Capacity as determined d etermined by such test shall be the difference between the reading taken at the end of the six (6) hour period and the reading taken at the beginning of such period, divided by six (6) and such result adjusted to Reference ConditionsCondition; provided, that t hat, subject to t o Section 2.9(b)●[ ], the initial Tested Capacity shall not be considered to have been be en established unless un less the result of such o f su ch determination is i s equal to or greater than the Contract Capacity and satisfies the minimum criteria for such test set forth in Schedule 7[●]. On At the completion of the Commissioning Tests, the initial Tested Capacity i nitial T ested C apacity (adjusted to Reference ConditionsCondition) shall be sha ll b e certified by the Engineer (the “Capacity Test Certificate”).

Appears in 1 contract

Sources: Engineering Procurement and Construction Contract

Tests Upon and After Synchronization of the Complex and Commissioning Tests. (a) After first synchronizing the Complex, initial operational testing of the Complex shall be conducted by the Company or its Contractors. Once the Company is satisfied that the Complex is capable of continued reliable operation, the Company shall request the Engineer to issue the Certificate of Readiness. Upon the issuance by the Engineer of the Certificate of Readiness, the Company shall so notify the Power Purchaser and carry out or cause its Contractors to carry out, the following tests (the “Commissioning Tests”), which if the Complex satisfies the minimum performance criteria thereforthere for, will result in the Complex being Commissioned and in the establishment of the Commercial Operations Date in accordance with Section 8.3(c)(iii): (i) initial Tested Capacity test; (ii) reliability run test; (iii) automatic voltage regulator operation testdroop; (iv) boiler/turbine Turbine governor operation (droop) testoperation; (v) reactive capability; (vi) minimum load capability; (vii) [response of Complex to step load changes]; and (viii) full load rejection. Minimum performance criteria for the Commissioning Tests are included in Schedule 7. (b) Reliability Run and Initial Tested Capacity. Upon completion of the reliability run test prerequisites as included in Schedule 7, the Company shall declare to the Power Purchaser the commencement of the reliability run testtest including the test under Section 8.3(a)(i). During the one hundred and sixty- sixty-eight (168) hour period of the reliability run test, the initial Tested Capacity of the Complex will be determined in the following manner: (i) The Complex shall be in operation at full output with normal auxiliaries and full colony load, if connected directly to the Complex, in service. (ii) The Company will declare to the Power Purchaser the commencement of the test and will record the reading of the Metering System. (iii) The test duration will be six (6) continuous hours and and, at the end of this period period, the Company will record the new reading of the Metering System. The initial Tested Capacity as determined by such test shall be the difference between the reading taken at the end of the six (6) hour period and the reading taken at the beginning of such period, divided by six (6) and such result adjusted to Reference Hydrological Conditions; provided, that that, subject to Section 2.9(b)2.9, the initial Tested Capacity shall not be considered to have been established unless the result of such determination is equal to or greater than the Contract Capacity and satisfies the minimum criteria for such test set forth in Schedule 7. On At the completion of the Commissioning Tests, the initial Tested Capacity (adjusted to Reference Hydrological Conditions) shall be certified by the Engineer (the “Capacity Test Certificate”).

Appears in 1 contract

Sources: Power Purchase Agreement

Tests Upon and After Synchronization of the Complex and Commissioning Tests. (a) After first synchronizing the Complex, initial operational testing of the Complex shall be conducted by the Company Seller or its Contractors. Once the Company is On being satisfied that the Complex is capable of continued reliable operation, the Company Seller shall request the Engineer to issue the Certificate of ReadinessReadiness of Commissioning Tests. Upon the issuance by the Engineer of the Certificate of ReadinessReadiness of Commissioning Tests, the Company Seller shall so notify the Power Purchaser and carry out or cause its Contractors to carry out, the following tests (the “Commissioning Tests”)Tests”)and/or shall produce “factory acceptance test” (FAT) reports and/or “site test results” (as relevant) as mentioned in this Section 8.3, which which, if the Complex satisfies the minimum performance criteria therefor, will result in the Complex being Commissioned and in the establishment of the Commercial Operations Date in accordance with Section 8.3(c)(iii): (i) initial Tested Capacity test; (ii) reliability run test; (iii) automatic voltage regulator operation test; (iv) boiler/turbine governor operation (droop) test; (v) reactive capability; (vi) minimum load capability; (vii) response of Complex to step load changes; and (viii) full load rejection. Minimum performance criteria for the Commissioning Tests are included in Schedule 7. (b) Reliability Run and Initial Tested Capacity. Upon completion of the reliability run test prerequisites as included in Schedule 7, the Company shall declare to the Power Purchaser the commencement of the reliability run test. During the one hundred and sixty- eight (168) hour period of the reliability run test, the initial Tested Capacity of the Complex will be determined in the following manner8.4: (i) Reliability Run Test: A test for a period of twenty four (24) hours, which shall include three (3) continuous hours at maximum continuous rating however any interruption caused due to Grid (in)stability or failure shall not be considered as interruption to this test (“Reliability Run Test”); The Complex Seller shall give the Purchaser no less than twenty four (24) hours prior written notice of the first Reliability Run Test. The Purchaser may observe the Reliability Run Test. The Seller shall be in operation at full output with normal auxiliaries and full colony load, if connected directly entitled to carry out as many Reliability Run Tests as are required to satisfy the Complex, in servicerelevant criteria. (ii) Contract Capacity Test: A test (“Contract Capacity Test") in accordance with the following criteria: (A) The Company will declare to Contract Capacity shall be determined/finalised by measuring the Power Purchaser electrical energy at the commencement of the test and will record the reading of delivery point recorded by the Metering SystemSystem while all generating units are operating at 100% base load. (iiiB) The test duration will shall be six conducted for three (63) continuous hours based on the relevant ASME, ISO and IEC standards for the plant using plant instrumentation and the Metering System in the presence of the Engineer. For the avoidance of doubt: (i) the Seller can request for up to three (3) attempts to carry out the aforementioned testing; (ii) the Seller may at its sole discretion interrupt any such test (during the three (3) hour testing period) and thereafter request for repetition of such test after a minimum of forty-eight (48) hours; (iii) the Purchaser shall ensure the availability of the necessary Grid System Frequency and Grid System Voltage – and any interruption caused by the non-availability of (or faults in) the Grid System shall not affect the overall testing time of three (3) hours; (iv) during such testing, normal auxiliaries shall remain in operation; and (v) colony/residential load shall be accounted for while calculating the net electrical load (in case the colony/residential lodge is attached to the plant load). (C) At the end of this period the Company will testing period, the Seller shall record the new reading of the Metering System. The initial Tested ; and the Contract Capacity (as determined by such test test) shall be the difference between the reading taken at the end of the six abovementioned three (63) hour period and the reading taken at the beginning of such period, divided by six three (6) and such result adjusted to Reference Conditions; provided, that , subject to Section 2.9(b3), the initial Tested Capacity shall not be considered to have been established unless the result . Upon completion of such determination is equal to or greater than the Contract Capacity and satisfies the minimum criteria for such test set forth in Schedule 7. On the completion of the Commissioning Tests, the initial Tested Capacity (adjusted to Reference Conditions) shall be certified by the Engineer shall issue a certificate (the “Capacity Test Certificate”)) which shall finally determine the Contract Capacity. (iii) FAT in relation to automatic voltage regulator droop; (iv) FAT in relation to turbine governor operation; such FAT shall be based on mechanical run test of turbine at manufacturer’s facility. In addition, over speed trip (mechanical and electronic) shall be performed on Site and the site test results shall be provided; (v) OEM Generator capability curve shall be provided in relation to reactive capability; (vi) Not Used; (vii) Not Used; (viii) Not Used After successful completion of the Commissioning Tests)and the issuance of the Capacity Test Certificate, the Engineer shall issue a Certificate of Commissioning of the Complex to the Purchaser and the Seller.

Appears in 1 contract

Sources: Energy Purchase Agreement