The Determination. 6.1 As expeditiously as possible after the receipt of the submissions or after any conference and, in any event not later than three months after the commencement of the Process unless the time has been extended by agreement between the Parties, the Expert shall determine the dispute between the Parties and notify such determination in writing to the Parties. 6.2 The notice of the determination shall include a brief statement of the reasons for the determination. 6.3 The Expert shall reach the determination on the basis of the information received from the Parties and on the basis of the Expert's own expertise. 6.4 Where the determination made by the Expert contains - (a) a clerical mistake; (b) an error arising from an accidental slip or omission; (c) a material miscalculation of figures or a material mistake in the description of any person, thing or matter; or (d) a defect of form, the Expert shall correct the determination.
Appears in 1 contract
Sources: Tweed River Entrance Sand Bypassing Project Agreement
The Determination. 6.1 As expeditiously as possible after the receipt of the submissions or after any conference and, in any event not later than three months after the commencement of the Process unless the time has been extended by agreement between the Parties, the Expert shall determine the dispute between the Parties and notify such determination in writing to the Parties.
6.2 The notice of the determination shall include a brief statement of the reasons for the determination.
6.3 The Expert shall reach the determination on the basis of the information received from the Parties and on the basis of the Expert's own expertise.
6.4 Where the determination made by the Expert contains -contains—
(a) a clerical mistake;
(b) an error arising from an accidental slip or omission;
(c) a material miscalculation of figures or a material mistake in the description of any person, thing or matter; or
(d) a defect of form, the Expert shall correct the determination.