Time and Delivery. 10.1. If access to Purchaser sites is necessary for the delivery or provision of the Supplies, the Purchaser will allow access at reasonable times. The Supplier will observe the Purchaser's health & safety and security policies and procedures, and access may be denied for non-compliance. 10.2. The Supplier must comply with the Health & Safety at Work Act 2015 and accordingly ensure as far as is reasonably practicable that the health and safety of its personnel, the personnel of the Purchaser and of other persons is not put at risk from work carried out in the performance of these Terms and that it does not do anything likely to give rise to an improvement or prohibition notice or regulatory breach under such Act. 10.3. The times and dates stated in the Purchase Order for delivery or completion (including any extension of such time or date granted in writing by Lakes District) shall be binding and are of the essence of the Agreement. 10.4. The Supplier shall deliver Product without additional charge to Lakes District, to the address stated in the Purchase Order by the stated dates for delivery. 10.5. The Supplier shall not charge Lakes District for wrapping, packing, cartons, boxing or preparing the Products for shipment unless authority for such charge is expressly incorporated in the Agreement. 10.6. The Supplier must ensure that: (a) All cases, crates and packages to be used in packaging the goods shall be protected against corrosion, weather damage, condensation, distortion, damage by vermin and the ingress of foreign matter; (b) All packaging material shall comply with all legal requirements in New Zealand which are relevant to such materials, including the requirements of the Ministry of Primary Industries and the Ministry of Agriculture and Fisheries. The Supplier shall take all necessary steps to ensure that the packing materials comply with such rules and the Supplier indemnifies Lakes District against all losses, claims or expenses suffered or incurred by it as a result of such packing material not so complying; (c) A packing slip is provided with all goods; (d) The number on the Purchase Order must be quoted on all packing slips, delivery dockets, invoices and related documents, and shown clearly on all consignments. 10.7. The Supplier shall ensure that prior to the delivery or use of any Hazardous Substance on Site, the Supplier: (a) applies appropriate labelling; (b) provides Lakes District with a copy of the current Safety Data Sheet for such Hazardous Substance that complies with any relevant Code of Practice; (c) provides Lakes District with a completed risk assessment if Services include the use of such Hazardous Substances; and (d) complies in all respects with the requirements of the Hazardous Substances and New Organisms Act 1996 and related regulations.
Appears in 2 contracts
Sources: Terms and Conditions of Purchase, Terms and Conditions of Purchase
Time and Delivery. 10.1. If access to Purchaser sites is necessary for the delivery or provision of the Supplies, the Purchaser will allow access at reasonable times. The Supplier will observe the Purchaser's health & safety and security policies and procedures, and access may be denied for non-compliance.
10.2. The Supplier must comply with the Health & Safety at Work Act 2015 and accordingly ensure as far as is reasonably practicable that the health and safety of its personnel, the personnel of the Purchaser and of other persons is not put at risk from work carried out in the performance of these Terms and that it does not do anything likely to give rise to an improvement or prohibition notice or regulatory breach under such Act.
10.38.1. The times and dates stated in the Purchase Order for delivery or completion (including any extension of such time or date granted in writing by Lakes DistrictCOUNCIL) shall be binding and are of the essence essence.
8.2. If it appears that the Goods or Services will not be delivered or completed within the time and dates stated in the Purchase Order, the supplier must immediately notify the COUNCIL of the Agreementanticipated delay. In the event of the delay occurring COUNCIL reserve the right to terminate all or part of the Agreement (without compensation to the Supplier).
10.48.3. The Supplier shall deliver Product or arrange delivery of Products without additional charge to Lakes DistrictCOUNCIL, to the address stated in the Purchase Order by the stated dates for deliveryOrder.
10.58.4. The Supplier shall not charge Lakes District COUNCIL for wrapping, packing, cartons, boxing or preparing the Products for shipment unless authority for such charge is expressly incorporated in the Agreement.
10.68.5. The Supplier must ensure that:
(a) All cases, crates and packages to be used in packaging the goods Products shall be protected against corrosion, weather damage, condensation, distortion, damage by vermin and the ingress of foreign matter;
(b) All packaging material shall comply with all legal requirements in New Zealand which are relevant to such materials, including the requirements of the Ministry of Primary Industries Forestry and the Ministry of Agriculture and Fisheries. The Supplier shall take all necessary steps to ensure that the packing materials comply with such rules and the Supplier indemnifies Lakes District COUNCIL against all losses, claims or expenses suffered or incurred by it as a result of such packing material not so complying;
(c) A packing slip is provided with all goods;
(d) The number on the Purchase Order must be quoted on all packing slips, delivery dockets, invoices and related documents, and shown clearly on all consignments.
10.78.6. The Supplier shall ensure that prior to the delivery or use of any Hazardous Substance on Site, the Supplier:
(a) applies appropriate labellinglabelling to the Product;
(b) provides Lakes District COUNCIL with a copy of the current Safety Data Sheet for such Hazardous Substance that complies with any relevant Code of Practice;
(c) provides Lakes District COUNCIL with a completed risk assessment if Services include the use of such Hazardous Substances; and;
(d) complies in all respects with the requirements of the Hazardous Substances and New Organisms Act 1996 and related regulations; and
(e) complies with the health and safety requirements at clause 17.
Appears in 1 contract
Sources: Terms and Conditions of Purchase
Time and Delivery. 10.1. If access to Purchaser sites is necessary for the delivery or provision of the Supplies, the Purchaser will allow access at reasonable times. The Supplier will observe the Purchaser's health & safety and security policies and procedures, and access may be denied for non-compliance.
10.2. The Supplier must comply with the Health & Safety at Work Act 2015 and accordingly ensure as far as is reasonably practicable that the health and safety of its personnel, the personnel of the Purchaser and of other persons is not put at risk from work carried out in the performance of these Terms and that it does not do anything likely to give rise to an improvement or prohibition notice or regulatory breach under such Act.
10.38.1. The times and dates stated in the Purchase Order for delivery or completion (including any extension of such time or date granted in writing by Lakes DistrictCOUNCIL) shall be binding and are of the essence essence.
8.2. If it appears that the Goods or Services will not be delivered or completed within the time and dates stated in the Purchase Order, the supplier must immediately notify the COUNCIL of the Agreementanticipated delay. In the event of the delay occurring COUNCIL reserve the right to terminate all or part of the Agreement (without compensation to the Supplier).
10.48.3. The Supplier shall deliver Product or arrange delivery of Products without additional charge to Lakes DistrictCOUNCIL, to the address stated in the Purchase Order by the stated dates for deliveryOrder.
10.58.4. The Supplier shall not charge Lakes District COUNCIL for wrapping, packing, cartons, boxing or preparing the Products for shipment unless authority for such charge is expressly incorporated in the Agreement.
10.68.5. The Supplier must ensure that:
(a) All cases, crates and packages to be used in packaging the goods Products shall be protected against corrosion, weather damage, condensation, distortion, damage by vermin and the ingress of foreign matter;
(b) All packaging material shall comply with all legal requirements in New Zealand which are relevant to such materials, including the requirements of the Ministry of Primary Industries Forestry and the Ministry of Agriculture and Fisheries. The Supplier shall take all necessary steps to ensure that the packing materials comply with such rules and the Supplier indemnifies Lakes District COUNCIL against all losses, claims or expenses suffered or incurred by it as a result of such packing material not so complying;
(c) A packing slip is provided with all goods;
(d) The number on the Purchase Order must be quoted on all packing slips, delivery dockets, invoices and related documents, and shown clearly on all consignments.
10.78.6. The Supplier shall ensure that prior to the delivery or use of any Hazardous Substance on Site, the Supplier:
(a) applies appropriate labellinglabelling to the Product;
(b) provides Lakes District COUNCIL with a copy of the current Safety Data Sheet for such Hazardous Substance that complies with any relevant Code of Practice;
(c) provides Lakes District COUNCIL with a completed risk assessment if Services include the use of such Hazardous Substances; and;
(d) complies in all respects with the requirements of the Hazardous Substances and New Organisms Act 1996 ▇▇▇ ▇▇▇▇▇▇▇▇▇ ▇▇▇ ▇▇▇▇ and related regulations; and
(e) complies with the health and safety requirements at clause 17.