Time and Materials Change Orders. For a time-and-materials change, County shall determine the adjustment to the Contract Price on the basis of actual costs as follows: (a) Cost of materials and supplies (show actual unit cost multiplied by actual quantity). The cost of materials shall be at invoice price or the lowest current price at which such materials are locally available and delivered to the job site in the quantities involved, plus freight and delivery. County reserves the right to approve materials and sources of supply or to supply materials to Contractor if necessary for the progress of the work. No markup for overhead and profit shall be applied to any material provided by County. (b) Tool and equipment rental. County will not pay for the use of tools that individually have a replacement value of $200 or less. Regardless of ownership, the equipment rental rates shall be based upon the edition of equipment rental rates published by the Caltrans Division of Construction, or locally available rate or other reference acceptable to County current as of the date the changed work is performed. The rental rates paid shall include the cost of fuel, oil lubrication, supplies, small tools, necessary attachments, repairs and maintenance of any kind, depreciation, storage, insurance, and all incidents. Necessary loading and transportation costs for equipment used on the changed work shall be included. If equipment is used intermittently and, when not in use, could be returned to its rental source at less expense to County than holding it at the work site, it shall be returned, unless Contractor elects to keep it at the work site at no expense to County. All equipment shall be acceptable to County, in good working condition, and suitable for the purpose for which it is to be used. Manufacturers' ratings and approved modifications shall be used to classify equipment and it shall be powered by a unit of at least the minimum rating recommended by the manufacturer. The reported rental time for equipment already at the work site shall be the duration of its use on the changed work, commencing at the time it is first put into actual operation on the changed work, plus the time required to move it from its previous site and back or to a closer site. Contractor shall submit invoices for tool and equipment rental costs. If Contractor does not submit invoices, County may establish the rental costs at the lowest price which was current at the time the changed work was performed. (c) Cost of labor (show actual total hourly rate multiplied by actual hours spent on changed work). The costs of labor shall not exceed the wages prevailing for each craft or type of workers performing the changed work at the time the changed work is done. The costs of labor shall include the actual basic hourly rate, plus employer's actual regular payments for health and welfare, pension, vacation or holiday, training, and other direct costs resulting from federal, State or local laws, as well as assessments or benefits required by lawful collective bargaining agreements and shall be supported by payroll records. The costs of labor shall not include any amount for bonuses or extraordinary vacation or holidays. The use of a labor classification that would increase the changed work cost will not be permitted unless Contractor establishes the necessity for such additional costs. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental. The labor cost for foremen shall be proportional to all of their assigned work and only that applicable to changed work shall be paid. Non-direct labor costs including superintendence shall be considered part of the markup for overhead and profit below. (d) Sales taxes on materials (percentage of item (a), above). (e) Payroll tax on labor (percentage of item (c), above). (f) Insurance (workers' compensation and liability insurance). (g) Other Items. County may authorize other items that may be required for the changed work. Such items include labor, services, material, and equipment that are different in their nature from those required for the work and that are of a type not ordinarily available from Contractor or any of its subcontractors. Contractor shall submit invoices covering all such items in detail. (h) Overhead and profit. Contractor shall receive a maximum 15% for overhead and profit on above items if Contractor uses its own forces to perform changed work. If Contractor 's subcontractor's forces perform changed work, then the subcontractor shall be entitled to a maximum of 15% on above items for its overhead and profit and Contractor shall be entitled to a maximum of 6% on above items for its overhead and profit on the changed work. County will pay only one overhead and profit markup of 6% for Contractor and one markup of 15% for the subcontractor in connection with changed work, regardless of the actual number of intervening subcontractors involved in the changed work. County will not pay any overhead or profit for omitted work. (i) Bond (1% of above items). Contractor shall keep and present, in such form as County may prescribe, an itemized accounting of the costs or savings attributable to the changed work, together with appropriate supporting data. The accounting shall include a daily job record in quadruplicate containing a detailed description of: the labor (workers, classifications, and hours worked); quantities of materials used; equipment used (identifying the equipment and the hours of use); and any other services and expenditures in such detail as County may require. Upon being signed and agreed to by County and Contractor at the end of each day's performance, the daily job record will become the basis for payment for the changed work. But such agreement shall not preclude the County from thereafter conducting an audit and adjusting the basis for payment. Failure by Contractor to submit the daily report by the close of the next working day may constitute a waiver of any rights for that day. Upon request by County, Contractor shall permit County to inspect Contractor's original estimate for the Project, subcontract agreements, or purchase orders relating to the change. Upon completion of the changed work ordered to be performed on a time and materials basis, County will then issue a unilateral Change Order adjusting the Contract Price according to the actual costs incurred and, if appropriate, adjusting the Contract Time.
Appears in 2 contracts
Sources: Contract, Construction Contract
Time and Materials Change Orders. For a time-and-materials change, County shall determine the adjustment to the Contract Price on the basis of actual costs as follows:
(a) Cost of materials and supplies (show actual unit cost multiplied by actual quantity). The cost of materials shall be at invoice price or the lowest current price at which such materials are locally available and delivered to the job site in the quantities involved, plus freight and delivery. County reserves the right to approve materials and sources of supply or to supply materials to Contractor CM if necessary for the progress of the work. No markup for overhead and profit shall be applied to any material provided by County.
(b) Tool and equipment rental. County will not pay for the use of tools that individually have a replacement value of $200 or less. Regardless of ownership, the equipment rental rates shall be based upon the edition of equipment rental rates published by the Caltrans Division of Construction, or locally available rate or other reference acceptable to County current as of the date the changed work is performed. The rental rates paid shall include the cost of fuel, oil lubrication, supplies, small tools, necessary attachments, repairs and maintenance of any kind, depreciation, storage, insurance, and all incidents. Necessary loading and transportation costs for equipment used on the changed work shall be included. If equipment is used intermittently and, when not in use, could be returned to its rental source at less expense to County than holding it at the work site, it shall be returned, unless Contractor CM elects to keep it at the work site at no expense to County. All equipment shall be acceptable to County, in good working condition, and suitable for the purpose for which it is to be used. Manufacturers' ratings and approved modifications shall be used to classify equipment and it shall be powered by a unit of at least the minimum rating recommended by the manufacturer. The reported rental time for equipment already at the work site shall be the duration of its use on the changed work, commencing at the time it is first put into actual operation on the changed work, plus the time required to move it from its previous site and back or to a closer site. Contractor CM shall submit invoices for tool and equipment rental costs. If Contractor CM does not submit invoices, County may establish the rental costs at the lowest price which was current at the time the changed work was performed.
(c) Cost of labor (show actual total hourly rate multiplied by actual hours spent on changed work). The costs of labor shall not exceed the wages prevailing for each craft or type of workers performing the changed work at the time the changed work is done. The costs of labor shall include the actual basic hourly rate, plus employer's actual regular payments for health and welfare, pension, vacation or holiday, training, and other direct costs resulting from federal, State or local laws, as well as assessments or benefits required by lawful collective bargaining agreements and shall be supported by payroll records. The costs of labor shall not include any amount for bonuses or extraordinary vacation or holidays. The use of a labor classification that would increase the changed work cost will not be permitted unless Contractor CM establishes the necessity for such additional costs. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental. The labor cost for foremen shall be proportional to all of their assigned work and only that applicable to changed work shall be paid. Non-direct labor costs including superintendence shall be considered part of the markup for overhead and profit below.
(d) Sales taxes on materials (percentage of item (a), above).
(e) Payroll tax on labor (percentage of item (c), above).
(f) Insurance (workers' compensation and liability insurance).
(g) Other Items. County may authorize other items that may be required for the changed work. Such items include labor, services, material, and equipment that are different in their nature from those required for the work and that are of a type not ordinarily available from Contractor or any of its subcontractors. Contractor shall submit invoices covering all such items in detail.
(h) Overhead and profit. Contractor shall receive a maximum 15% for overhead and profit on above items if Contractor uses its own forces to perform changed work. If Contractor 's subcontractor's forces perform changed work, then the subcontractor shall be entitled to a maximum of 15% on above items for its overhead and profit and Contractor shall be entitled to a maximum of 6% on above items for its overhead and profit on the changed work. County will pay only one overhead and profit markup of 6% for Contractor and one markup of 15% for the subcontractor in connection with changed work, regardless of the actual number of intervening subcontractors involved in the changed work. County will not pay any overhead or profit for omitted work.
(i) Bond (1% of above items). Contractor shall keep and present, in such form as County may prescribe, an itemized accounting of the costs or savings attributable to the changed work, together with appropriate supporting data. The accounting shall include a daily job record in quadruplicate containing a detailed description of: the labor (workers, classifications, and hours worked); quantities of materials used; equipment used (identifying the equipment and the hours of use); and any other services and expenditures in such detail as County may require. Upon being signed and agreed to by County and Contractor at the end of each day's performance, the daily job record will become the basis for payment for the changed work. But such agreement shall not preclude the County from thereafter conducting an audit and adjusting the basis for payment. Failure by Contractor to submit the daily report by the close of the next working day may constitute a waiver of any rights for that day. Upon request by County, Contractor shall permit County to inspect Contractor's original estimate for the Project, subcontract agreements, or purchase orders relating to the change. Upon completion of the changed work ordered to be performed on a time and materials basis, County will then issue a unilateral Change Order adjusting the Contract Price according to the actual costs incurred and, if appropriate, adjusting the Contract Time.
Appears in 2 contracts
Sources: Construction Phase Services, Construction Phase Services
Time and Materials Change Orders. For a time-and-materials change, County shall determine the adjustment to the Contract Price on the basis of actual costs as follows:
(a) Cost of materials and supplies (show actual unit cost multiplied by actual quantity). The cost of materials shall be at invoice price or the lowest current price at which such materials are locally available and delivered to the job site in the quantities involved, plus freight and delivery. County reserves the right to approve materials and sources of supply or to supply materials to Contractor D-BE if necessary for the progress of the work. No markup for overhead and profit shall be applied to any material provided by County.
(b) Tool and equipment rental. County will not pay for the use of tools that individually have a replacement value of $200 or less. Regardless of ownership, the equipment rental rates shall be based upon the edition of equipment rental rates published by the Caltrans Division of Construction, or locally available rate or other reference acceptable to County current as of the date the changed work is performed. The rental rates paid shall include the cost of fuel, oil lubrication, supplies, small tools, necessary attachments, repairs and maintenance of any kind, depreciation, storage, insurance, and all incidents. Necessary loading and transportation costs for equipment used on the changed work shall be included. If equipment is used intermittently and, when not in use, could be returned to its rental source at less expense to County than holding it at the work site, it shall be returned, unless Contractor D-BE elects to keep it at the work site at no expense to County. All equipment shall be acceptable to County, in good working condition, and suitable for the purpose for which it is to be used. Manufacturers' ratings and approved modifications shall be used to classify equipment and it shall be powered by a unit of at least the minimum rating recommended by the manufacturer. The reported rental time for equipment already at the work site shall be the duration of its use on the changed work, commencing at the time it is first put into actual operation on the changed work, plus the time required to move it from its previous site and back or to a closer site. Contractor D-BE shall submit invoices for tool and equipment rental costs. If Contractor D-BE does not submit invoices, County may establish the rental costs at the lowest price which was current at the time the changed work was performed.
(c) Cost of labor (show actual total hourly rate multiplied by actual hours spent on changed work). The costs of labor shall not exceed the wages prevailing for each craft or type of workers performing the changed work at the time the changed work is done. The costs of labor shall include the actual basic hourly rate, plus employer's actual regular payments for health and welfare, pension, vacation or holiday, training, and other direct costs resulting from federal, State or local laws, as well as assessments or benefits required by lawful collective bargaining agreements and shall be supported by payroll records. The costs of labor shall not include any amount for bonuses or extraordinary vacation or holidays. The use of a labor classification that would increase the changed work cost will not be permitted unless Contractor D-BE establishes the necessity for such additional costs. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental. The labor cost for foremen shall be proportional to all of their assigned work and only that applicable to changed work shall be paid. Non-direct labor costs including superintendence shall be considered part of the markup for overhead and profit below.
(d) Sales taxes on materials (percentage of item (a), above).
(e) Payroll tax on labor (percentage of item (c), above).
(f) Insurance (workers' compensation and liability insurance).
(g) Other Items. County may authorize other items that may be required for the changed work. Such items include labor, services, material, and equipment that are different in their nature from those required for the work and that are of a type not ordinarily available from Contractor or any of its subcontractors. Contractor shall submit invoices covering all such items in detail.
(h) Overhead and profit. Contractor shall receive a maximum 15% for overhead and profit on above items if Contractor uses its own forces to perform changed work. If Contractor 's subcontractor's forces perform changed work, then the subcontractor shall be entitled to a maximum of 15% on above items for its overhead and profit and Contractor shall be entitled to a maximum of 6% on above items for its overhead and profit on the changed work. County will pay only one overhead and profit markup of 6% for Contractor and one markup of 15% for the subcontractor in connection with changed work, regardless of the actual number of intervening subcontractors involved in the changed work. County will not pay any overhead or profit for omitted work.
(i) Bond (1% of above items). Contractor shall keep and present, in such form as County may prescribe, an itemized accounting of the costs or savings attributable to the changed work, together with appropriate supporting data. The accounting shall include a daily job record in quadruplicate containing a detailed description of: the labor (workers, classifications, and hours worked); quantities of materials used; equipment used (identifying the equipment and the hours of use); and any other services and expenditures in such detail as County may require. Upon being signed and agreed to by County and Contractor at the end of each day's performance, the daily job record will become the basis for payment for the changed work. But such agreement shall not preclude the County from thereafter conducting an audit and adjusting the basis for payment. Failure by Contractor to submit the daily report by the close of the next working day may constitute a waiver of any rights for that day. Upon request by County, Contractor shall permit County to inspect Contractor's original estimate for the Project, subcontract agreements, or purchase orders relating to the change. Upon completion of the changed work ordered to be performed on a time and materials basis, County will then issue a unilateral Change Order adjusting the Contract Price according to the actual costs incurred and, if appropriate, adjusting the Contract Time.
Appears in 1 contract
Sources: Construction Contract
Time and Materials Change Orders. For a time-and-materials change, County shall determine the adjustment to the Contract Price on the basis of actual costs as follows:
(a) A. Cost of materials and supplies (show actual unit cost multiplied by actual quantity). The cost of materials shall be at invoice price or the lowest current price at which such materials are locally available and delivered to the job site in the quantities involved, plus freight and delivery. County reserves the right to approve materials and sources of supply or to supply materials to Contractor if necessary for the progress of the work. No markup for overhead and profit shall be applied to any material provided by County.supply
(b) B. Tool and equipment rental. County will not pay for the use of tools that individually have a replacement value of $200 or less. Regardless of ownership, the equipment rental rates shall be based upon the edition of equipment rental rates published by the Caltrans Division of Construction, or locally available rate or other reference acceptable to County current as of the date the changed work is performed. The rental rates paid shall include the cost of fuel, oil lubrication, supplies, small tools, necessary attachments, repairs and maintenance of any kind, depreciation, storage, insurance, and all incidents. Necessary loading and transportation costs for equipment used on the changed work shall be included. If equipment is used intermittently and, when not in use, could be returned to its rental source at less expense to County than holding it at the work site, it shall be returned, unless Contractor D-BE elects to keep it at the work site at no expense to County. All equipment shall be acceptable to County, in good working condition, and suitable for the purpose for which it is to be used. Manufacturers' ratings and approved modifications shall be used to classify equipment and it shall be powered by a unit of at least the minimum rating recommended by the manufacturer. The reported rental time for equipment already at the work site shall be the duration of its use on the changed work, commencing at the time it is first put into actual operation on the changed work, plus the time required to move it from its previous site and back or to a closer site. Contractor D-BE shall submit invoices for tool and equipment rental costs. If Contractor D-BE does not submit invoices, County may establish the rental costs at the lowest price which was current at the time the changed work was performed.
(c) C. Cost of labor (show actual total hourly rate multiplied by actual hours spent on changed work). The costs of labor shall not exceed the wages prevailing for each craft or type of workers performing the changed work at the time the changed work is done. The costs of labor shall include the actual basic hourly rate, plus employer's actual regular payments for health and welfare, pension, vacation or holiday, training, and other direct costs resulting from federal, State or local laws, as well as assessments or benefits required by lawful collective bargaining agreements and shall be supported by payroll records. The costs of labor shall not include any amount for bonuses or extraordinary vacation or holidays. The use of a labor classification that would increase the changed work cost will not be permitted unless Contractor D-BE establishes the necessity for such additional costs. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental. The labor cost for foremen shall be proportional to all of their assigned work and only that applicable to changed work shall be paid. Non-direct labor costs including superintendence shall be considered part of the markup for overhead and profit below.
(d) D. Sales taxes on materials (percentage of item (a)A, above).
(e) E. Payroll tax on labor (percentage of item (c)C, above).
(f) F. Insurance (workers' compensation and liability insurance).
(g) G. Other Items. County may authorize other items that may be required for the changed work. Such items include labor, services, material, and equipment that are different in their nature from those required for the work and that are of a type not ordinarily available from Contractor D-BE or any of its subcontractors. Contractor D-BE shall submit invoices covering all such items in detail.
(h) H. Overhead and profit. Contractor D-BE shall receive a maximum 15% amount not to exceed the Construction Fee Percentage indicated in Attachment B “Cost/Compensation” for overhead and profit on above items if Contractor D-BE uses its own forces to perform changed work. If Contractor D-BE's subcontractor's forces perform changed work, then the subcontractor shall be entitled to a maximum of 15% on above items for its overhead and profit and Contractor D-BE shall be entitled to a maximum of 6% on above items for its overhead and profit on the changed work. County will pay only one overhead and profit markup of 6% for Contractor D-BE and one markup of 15% for the subcontractor in connection with changed work, regardless of the actual number of intervening subcontractors involved in the changed work. County will not pay any overhead or profit for omitted work. Regardless of whether the equitable adjustment associated with changed work is recorded through a lump sum or time-and-materials Change Order, the amount County pays for overhead and profit shall be D-BE's only compensation for: all costs of supervision, superintendence, and scheduling; wages of timekeepers, watchmen, and clerks; tools individually valued at $200 or less; incidentals; any and all field and home office expenses; costs of estimating and preparing change orders; all impact costs including but not limited to lost productivity associated with "learning curves," "productivity factors," and "ripple effects"; and all other expenses not included in itemized costs.
I. Premiums for all bonds and insurance (i) Bond (1the maximum amount for this shall be 2% of above items). Contractor items and D-BE shall keep and present, provide documentation demonstrating it will actually incur an increase in such form as County may prescribe, an itemized accounting of the insurance costs or savings directly attributable to the changed work, together with appropriate supporting data. The accounting shall include a daily job record in quadruplicate containing a detailed description of: the labor (workers, classifications, and hours workedchange); quantities of materials used; equipment used (identifying the equipment and the hours of use); and any other services and expenditures in such detail as .
J. County may require. Upon being signed and agreed to by County and Contractor at the end of each dayreject D-BE's performanceproposal, the daily job record will become the basis for payment for the changed work. But such agreement shall not preclude the County from thereafter conducting an audit and adjusting the basis for payment. Failure by Contractor to submit the daily report by the close may negotiate with D-BE a revision of the next working day may constitute a waiver of any rights for that day. Upon request by County, Contractor shall permit County to inspect Contractor's original estimate for the Project, subcontract agreementsrequested change and associated proposal, or purchase orders relating to may approve the change. Upon completion of the changed work ordered to be performed on D-BE's proposal and incorporate it into a time and materials basis, County will then issue a unilateral Change Order adjusting the Contract Price according to the actual costs incurred and, if appropriate, adjusting the Contract TimeOrder.
Appears in 1 contract
Time and Materials Change Orders. For a time-and-materials change, County shall determine the adjustment to the Contract Price on the basis of actual costs as follows:
(a) Cost of materials and supplies (show actual unit cost multiplied by actual quantity). The cost of materials shall be at invoice price or the lowest current price at which such materials are locally available and delivered to the job site in the quantities involved, plus freight and delivery. County reserves the right to approve materials and sources of supply or to supply materials to Contractor D-BE if necessary for the progress of the work. No markup for overhead and profit shall be applied to any material provided by County.
(b) Tool and equipment rental. County will not pay for the use of tools that individually have a replacement value of $200 or less. Regardless of ownership, the equipment rental rates shall be based upon the edition of equipment rental rates published by the Caltrans Division of Construction, or locally available rate or other reference acceptable to County current as of the date the changed work is performed. The rental rates paid shall include the cost of fuel, oil lubrication, supplies, small tools, necessary attachments, repairs and maintenance of any kind, depreciation, storage, insurance, and all incidents. Necessary loading and transportation costs for equipment used on the changed work shall be included. If equipment is used intermittently and, when not in use, could be returned to its rental source at less expense to County than holding it at the work site, it shall be returned, unless Contractor D-BE elects to keep it at the work site at no expense to County. All equipment shall be acceptable to County, in good working condition, and suitable for the purpose for which it is to be used. Manufacturers' ratings and approved modifications shall be used to classify equipment and it shall be powered by a unit of at least the minimum rating recommended by the manufacturer. The reported rental time for equipment already at the work site shall be the duration of its use on the changed work, commencing at the time it is first put into actual operation on the changed work, plus the time required to move it from its previous site and back or to a closer site. Contractor D- BE shall submit invoices for tool and equipment rental costs. If Contractor D-BE does not submit invoices, County may establish the rental costs at the lowest price which was current at the time the changed work was performed.
(c) Cost of labor (show actual total hourly rate multiplied by actual hours spent on changed work). The costs of labor shall not exceed the wages prevailing for each craft or type of workers performing the changed work at the time the changed work is done. The costs of labor shall include the actual basic hourly rate, plus employer's actual regular payments for health and welfare, pension, vacation or holiday, training, and other direct costs resulting from federal, State or local laws, as well as assessments or benefits required by lawful collective bargaining agreements and shall be supported by payroll records. The costs of labor shall not include any amount for bonuses or extraordinary vacation or holidays. The use of a labor classification that would increase the changed work cost will not be permitted unless Contractor D-BE establishes the necessity for such additional costs. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental. The labor cost for foremen shall be proportional to all of their assigned work and only that applicable to changed work shall be paid. Non-direct labor costs including superintendence shall be considered part of the markup for overhead and profit below.
(d) Sales taxes on materials (percentage of item (a), above).
(e) Payroll tax on labor (percentage of item (c), above).
(f) Insurance (workers' compensation and liability insurance).
(g) Other Items. County may authorize other items that may be required for the changed work. Such items include labor, services, material, and equipment that are different in their nature from those required for the work and that are of a type not ordinarily available from Contractor or any of its subcontractors. Contractor shall submit invoices covering all such items in detail.
(h) Overhead and profit. Contractor shall receive a maximum 15% for overhead and profit on above items if Contractor uses its own forces to perform changed work. If Contractor 's subcontractor's forces perform changed work, then the subcontractor shall be entitled to a maximum of 15% on above items for its overhead and profit and Contractor shall be entitled to a maximum of 6% on above items for its overhead and profit on the changed work. County will pay only one overhead and profit markup of 6% for Contractor and one markup of 15% for the subcontractor in connection with changed work, regardless of the actual number of intervening subcontractors involved in the changed work. County will not pay any overhead or profit for omitted work.
(i) Bond (1% of above items). Contractor shall keep and present, in such form as County may prescribe, an itemized accounting of the costs or savings attributable to the changed work, together with appropriate supporting data. The accounting shall include a daily job record in quadruplicate containing a detailed description of: the labor (workers, classifications, and hours worked); quantities of materials used; equipment used (identifying the equipment and the hours of use); and any other services and expenditures in such detail as County may require. Upon being signed and agreed to by County and Contractor at the end of each day's performance, the daily job record will become the basis for payment for the changed work. But such agreement shall not preclude the County from thereafter conducting an audit and adjusting the basis for payment. Failure by Contractor to submit the daily report by the close of the next working day may constitute a waiver of any rights for that day. Upon request by County, Contractor shall permit County to inspect Contractor's original estimate for the Project, subcontract agreements, or purchase orders relating to the change. Upon completion of the changed work ordered to be performed on a time and materials basis, County will then issue a unilateral Change Order adjusting the Contract Price according to the actual costs incurred and, if appropriate, adjusting the Contract Time.