Time Extension for Unidentified Utilities. If DB 1.1. Except as otherwise expressly provided in this Section 6.8.1, no time extension will be allowed on account of: (a) any delays attributable to any inaccuracy(ies) in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.
Appears in 2 contracts
Sources: Design Build Agreement, Design Build Agreement
Time Extension for Unidentified Utilities. If DBDB Contractor
1.1. Except as otherwise expressly provided in this Section 6.8.1, no time extension will be allowed on account of: (a) any delays attributable to any inaccuracy(ies) in the Utility Strip Map; or (b) the performance of Utility Adjustments for Unidentified Utilities.
Appears in 1 contract
Sources: Design Build Agreement