Common use of Time Extensions Clause in Contracts

Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 43 contracts

Sources: Agreement for Professional Planning Services, Security Guard Services Agreement, Agreement for the Child and Adult Care After School Food Service Program

Time Extensions. 2.03.1 3.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 15 contracts

Sources: Professional Services, Services Agreement, Energy Consulting Services Agreement

Time Extensions. 2.03.1 3.4.2.1 If Contractor Consultant requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor Consultant is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 10 contracts

Sources: Professional Services Agreement, Agreement for Professional on Call Planning Services, Professional Services

Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 ninety (90) days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 6 contracts

Sources: Agreement for Blower Repair/Replacement Services, Janitorial Cleaning Agreement, Security Guard Services Agreement

Time Extensions. 2.03.1 ‌ 3.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 3 contracts

Sources: Agreement for Long Range Dredging Operational Plan, Dredging Monitoring Contractor Services Agreement, Management Agreement

Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 daystime. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 3 contracts

Sources: Professional Services, Client Application Support Services Agreement, Services Agreement

Time Extensions. 2.03.1 3.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 2 contracts

Sources: Electronic Citation Solution Agreement, Agreement for Services

Time Extensions. 2.03.1 3.03.1. If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 2 contracts

Sources: Professional Services Agreement, Professional Services Agreement

Time Extensions. 2.03.1 If In addition to the authority of the Director to extend this Agreement pursuant to the terms of Section 4.03.1 hereinbelow, if Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 2 contracts

Sources: Professional Planning Services Agreement, Professional Planning Services Agreement

Time Extensions. 2.03.1 3.5.2.1 If Contractor Consultant requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing writing, but does not require amendment of this Agreement. Contractor Consultant is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 2 contracts

Sources: Agreement for Master Program Management Services for Disaster Related Projects Phase 2, Agreement for Master Program Management Services for Disaster Related Projects Phase 2

Time Extensions. 2.03.1 ‌ 3.3.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 2 contracts

Sources: Library Digital Databases and Collections Services Agreement, Library Digital Materials Services Agreement

Time Extensions. 2.03.1 ‌ 4.1 If the Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, Director may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Operation and Maintenance Services Agreement

Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the Chief Procurement Officer (CPO), may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Agreement for Professional Planning Services

Time Extensions. 2.03.1 ‌ 3.03.1. If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Agreement for Disaster Funding Financial Services

Time Extensions. 2.03.1 3.4.2.1. If Contractor requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing writing, but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Disaster Debris Monitoring Services Agreement

Time Extensions. 2.03.1 4.4.2.1. If Contractor requests an extension of time to complete its Contractor’s performance, then the Director, in consultation with the CPO, Director may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).delay(s).‌

Appears in 1 contract

Sources: Professional Services Agreement

Time Extensions. 2.03.1 3.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 ninety (90) days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Licensing Agreement

Time Extensions. 2.03.1 2.04.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Arbitrage Calculation and Consulting Services Agreement

Time Extensions. 2.03.1 3.4.1.1. If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, Director may extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing writing, but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Agreement for Case Management Intermediary Services

Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Security Guard Services Agreement

Time Extensions. 2.03.1 3.03.1 If Contractor requests an extension of time to complete its performance, then the DirectorCity Attorney, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Litigation Support Services Agreement

Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the DirectorCity Attorney, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: E Discovery Software and Services Agreement

Time Extensions. 2.03.1 ‌ 3.03.1 If Contractor Agency requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor Agency is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Contingent Workforce Services Agreement

Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Managed Telecommunications Maintenance Services Agreement

Time Extensions. 2.03.1 3.39.1 If Contractor the Director requests an extension of time to complete its Contractor’s performance, then the DirectorCPO may, in upon consultation with the CPO, may, in his or her sole discretionDirector involved, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Professional Services

Time Extensions. 2.03.1 2.04.1 If Contractor requests an extension of time to complete its performance, then the DirectorCity Controller, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Professional Services

Time Extensions. 2.03.1 3.4.1.1. If Contractor Consultant requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing writing, but does not require amendment of this Agreement. Contractor Consultant is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Professional Services

Time Extensions. 2.03.1 ‌ 3.5.1. If Contractor requests an extension of time to complete its performance, then the DirectorCity Attorney, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Document Management Software Agreement

Time Extensions. 2.03.1 3.4.3.1 If Contractor requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing but does not require amendment of this AgreementContract. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Professional Services

Time Extensions. 2.03.1 3.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Disaster Debris Removal Services Agreement

Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 thirty days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Professional Services

Time Extensions. 2.03.1 3.5.2.1. If Contractor requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: On Call Planning Services Agreement

Time Extensions. 2.03.1 ‌ 3.03.1. If Contractor Consultant requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 days. The extension must be in writing but does not require amendment of this Agreement. Contractor Consultant is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Disaster Recovery and Consulting Services Agreement

Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Fleet Management Department Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Contract for Maintenance and Repair Services

Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 ninety (90) days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Contract for Third Party Administrative Services

Time Extensions. 2.03.1 3.4.2.1 If Contractor requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing writing, but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Agreement for Security Guard Services

Time Extensions. 2.03.1 3.7.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, Director may, in his or her its sole discretion, extend the time so long as the extension does not exceed 90 180 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Agreement for the Administration of an Aviation Pole Banner Program

Time Extensions. 2.03.1 ‌ 3.5.1. If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).

Appears in 1 contract

Sources: Searchable Title Database Solution Agreement