Common use of Time for Completion of the Works Clause in Contracts

Time for Completion of the Works. If the carrying out of the Works or any part thereof is delayed and the delay is notified to the Authority in accordance with Clause 20.1 and such delay is attributable to: 20.4.1 a Compensation Event, then the provisions of Clause 39 (Compensation Events) shall apply; or 20.4.2 a Relief Event, then the provisions of Clause 40 (Relief Events) shall apply; or

Appears in 2 contracts

Sources: Residual Waste Treatment Contract, Residual Waste Treatment Contract