Common use of Time for Completion of the Works Clause in Contracts

Time for Completion of the Works. If any delay or anticipated failure to meet a Start on Site Date or a Planned Services Commencement Date or any relevant Long Stop Date, is notified to the Authority by the Contractor as being in the Contractor’s reasonable opinion attributable to: 16.4.1 a Compensation Event, then the provisions of clause 16.5 (Delays in Services Commencement Date due to a Compensation Event) shall apply; 16.4.2 a Relief Event, then the provisions of clause 51 (Relief Events) shall apply;

Appears in 2 contracts

Sources: Project Agreement, Project Agreement