Common use of Time for submittals Clause in Contracts

Time for submittals. Each submittal must be received by the A-E in time to permit 21calendar days for their review. If a submittal is not received in time to allow sufficient time, (calendar days) for the A-E's review without delaying construction, the ▇▇▇▇ shall reimburse Owner for the A-E's costs incurred by checking on an accelerated basis.

Appears in 4 contracts

Sources: Construction Contract, Construction Manager at Risk Construction Agreement, Construction Contract

Time for submittals. Each submittal must be received by the A-E in time to permit 21calendar days for their review. If a submittal is not received in time to allow sufficient time, (calendar days) for the A-E's review without delaying construction, the ▇▇▇▇ CM shall reimburse Owner County for the A-E's costs incurred by checking on an accelerated basis.

Appears in 2 contracts

Sources: Construction Phase Services, Construction Phase Services