Time Progress Schedule. (1) To show compliance with the requirements of Section 3.01 of the Agreement, provide and maintain a time progress schedule. After Contract Award, but before processing second progress payment application, the Contractor, unless otherwise directed by the University, shall submit to the University and the Consultant for their acceptance its proposed working plan and time progress schedule for all the work covered by the Contract, and shall include activities for preparation and submission of all Shop Drawings and Samples. (2) The working plan and time progress schedule shall be in the form of suitable charts, diagrams or bar graphs and shall be based on the Contractor's logic and time estimates. Such plan and schedule shall be sufficiently detailed to show clearly, in sequence, all salient features of the work of each trade including: the anticipated time of commencement and completion of such work and the interrelationship between such work, submission of Shop Drawings and Samples for approval, approval of Shop Drawings and Samples, placing of orders of materials, fabrication and delivery of materials, installation and testing of materials, contiguous or related work under other contracts, and other items pertinent to the work. (3) Phases of work shall include time in the schedule for training crews, acclimating trades to the sequence and apportionment of activities, additional meetings with the owner, consultant, Contractor and the significant subcontractors, and re-sequencing activities to recover from start-up delays typically caused by normal activities associated with the start-up of field work. (4) The aforesaid proposed working plan and schedule shall be revised by the Contractor until they are satisfactory to the University and the Consultant, and the same shall be periodically revised thereafter and submitted by the Contractor to the University and the Consultant for approval at such time or times as the University or the Consultant may request. (5) The proposed working plan and schedule, including any revision or revisions thereof, when approved by both the University and the Consultant shall be known as the Schedule of Record. The Schedule of Record, as the same may be revised from time to time by the Contractor and approved by the University and the Consultant, shall be strictly adhered to by the Contractor. (6) If through the fault of the Contractor or any subcontractor the Contractor shall fail to adhere to the time progress schedule, it must promptly adopt such other and additional means and methods of construction as will make up for the time lost and will assure completion in accordance with such schedule. (7) The failure of the Contractor to submit a Time Progress Schedule, the University's or the Consultant's acceptance of the Contractor's time progress schedule or lack of such acceptance, the means and/or methods of construction employed by the Contractor, including any revisions thereof, and/or its failure to revise the same shall not relieve the Contractor of its obligation to accomplish the result required by the Contract in the time specified on page 1 of the Agreement, nor shall the exercise of such right to reject, create or give rise to any claim, action or cause of action, legal, equitable or otherwise, against the Consultant or the University.
Appears in 1 contract
Sources: Construction Contract
Time Progress Schedule. (1) To show compliance with the requirements of Section 3.01 Within thirty (30) calendar days after receipt of the Agreement, provide and maintain a time progress schedule. After Contract Award, but before processing second progress payment applicationapproval of the Office of the State Comptroller, the Contractor, unless otherwise directed by the UniversityFund, shall submit to the University Fund and the Consultant for their acceptance approval its proposed working plan and time progress schedule for all the work covered by the Contract, and shall include activities for preparation and submission approval a proposed time schedule covering its first ninety (90) calendar days of all Shop Drawings and Samples.
(2) operation. The working plan and time progress schedule shall be in the form of suitable charts, diagrams or bar graphs and shall be based on the Contractor's logic and time estimates. Such plan and schedule shall be sufficiently detailed to show clearly, in sequence, all salient features of the work of each trade including: the anticipated time of commencement and completion of such work and the interrelationship between such work, submission of Shop Drawings and Samples for approval, approval of Shop Drawings and Samples, placing of orders of materials, fabrication and delivery of materials, installation and testing of materials, contiguous or related work under other contracts, and other items pertinent to the work.
(32) Phases Within ninety (90) calendar days after receipt of the approval of the Office of the State Comptroller, the contractor, unless otherwise directed by the Fund, shall submit to the Fund and the Consultant for their approval its proposed working plan and schedule for all the work covered by the Contract. Said proposed working plan and schedule shall include time be prepared in accordance with the form and requirements set forth in the schedule for training crews, acclimating trades to the sequence and apportionment of activities, additional meetings with the owner, consultant, Contractor and the significant subcontractors, and re-sequencing activities to recover from start-up delays typically caused by normal activities associated with the start-up of field workpreceding paragraph.
(43) The aforesaid proposed working plan and schedule shall be revised by the Contractor until they are satisfactory to the University Fund and the Consultant, and the same shall be periodically revised thereafter and submitted by the Contractor to the University Fund and the Consultant for approval at such time or times as the University Fund or the Consultant may request.
(54) The proposed working plan and schedule, including any revision or revisions thereof, when approved by both the University Fund and the Consultant shall be known as the Schedule of Recordtime progress schedule. The Schedule of Recordtime progress schedule, as the same may be revised from time to time by the Contractor and approved by the University Fund and the Consultant, shall be strictly adhered to by the Contractor.
(65) If through the fault of the Contractor or any subcontractor the Contractor shall fail to adhere to the time progress schedule, it must promptly adopt such other and additional means and methods of construction as will make up for the time lost and will assure completion in accordance with such schedule.
(76) The failure of the Contractor to submit a Time Progress Schedule, the UniversityFund's or the Consultant's acceptance approval of the Contractor's time progress schedule or lack of such acceptanceits time, the means and/or methods of construction employed by the Contractorconstruction, including any revisions thereof, and/or its their failure to revise reject the same shall not relieve the Contractor of its obligation to accomplish the result required by the Contract in the time specified on page 1 of the AgreementContract, nor shall the exercise of such right to reject, create or give rise to any claim, action or cause of action, legal, equitable or otherwise, against the Consultant or the UniversityFund.