Timely and Sustained Response. Developer shall ensure that the Large Generating Facility’s real power response to sustained frequency deviations outside of the deadband setting is automatically provided and shall begin immediately after frequency deviates outside of the deadband, and to the extent the Large Generating Facility has operating capability in the direction needed to
Appears in 2 contracts
Sources: Standard Large Generator Interconnection Service Agreement, Engineering, Procurement, and Construction Agreement
Timely and Sustained Response. Developer shall ensure that the Large Generating Facility’s real power response to sustained frequency deviations outside of the deadband setting is automatically provided and shall begin immediately after frequency deviates outside of the deadband, and to the extent the Large Generating Facility has operating capability in the direction needed tothe
Appears in 1 contract