Timely Submittal. Timely submittal and revision of the schedules is essential to ensure the satisfactory prosecution of the work. If the Contractor fails to submit the required schedule within the times stipulated, the Authority, in addition to all other remedies for such Default, may withhold payments otherwise due, and may direct the Contractor to take remedial measures, as provided in these Special Provisions. All schedules submitted shall show the effects of any occurrence upon which the Contractor has based or will base any claim or notice of potential claim for an extension of time, for additional compensation, or for both, and shall expressly call the Authority's attention thereto. Failure to do so in the case of any occurrence shall conclusively preclude the Contractor from asserting any claim for additional compensation, damages or schedule extension.
Appears in 2 contracts
Sources: Design, Build, Installation, Operation and Maintenance Agreement, Design, Build, Installation, Operation and Maintenance Agreement