Traffic Management. 3.3.1 Developer shall be responsible for the management of traffic on the Project (a) from the NTP2 until commencement of the Operating Period, for the entire Project and (b) from commencement of the Operating Period through the Term, for the O&M Limits only. Developer shall manage traffic so as to preserve and protect safety of traffic on the Project and Related Transportation Facilities and, to the maximum extent practicable, to avoid disruption, interruption or other adverse effects on traffic flow, throughput or level of service on the Project and Related Transportation Facilities. Developer shall conduct traffic management in accordance with all applicable Technical Provisions, Laws and Governmental Approvals, and in accordance with the Transportation Management Plan and Temporary Traffic Control Plans. 3.3.2 Developer shall prepare and submit to IFA for its approval a Transportation Management Plan for managing traffic. It shall address (a) during the initial construction of the Project, orderly and safe movement and diversion of traffic on Related Transportation Facilities,
Appears in 4 contracts
Sources: Public Private Agreement, Public Private Agreement, Public Private Agreement
Traffic Management.
3.3.1 Developer shall be responsible for the management of traffic on the Project (a) from the NTP2 until commencement of the Operating Period, for the entire Project and (b) from commencement of the Operating Period through the Term, for the O&M Limits only. Developer shall manage traffic so as to preserve and protect safety of traffic on the Project and Related Transportation Facilities and, to the maximum extent practicable, to avoid disruption, interruption or other adverse effects on traffic flow, throughput or level of service on the Project and Related Transportation Facilities. Developer shall conduct traffic management in accordance with all applicable Technical Provisions, Laws and Governmental Approvals, and in accordance with the Transportation Management Plan and Temporary Traffic Control Plans.
3.3.2 Developer shall prepare and submit to IFA for its approval a Transportation Management Plan for managing traffic. It shall address (a) during the initial construction of the Project, orderly and safe movement and diversion of traffic on Related Transportation Facilities,
Appears in 1 contract
Sources: Public Private Agreement
Traffic Management.
3.3.1 Developer shall be responsible for the management of traffic on the Project (a) from the NTP2 until commencement of the Operating Period, for the entire Project and (b) from commencement of the Operating Period through the Term, for the O&M Limits only. Developer shall manage traffic so as to preserve and protect safety of traffic on the Project and Related Transportation Facilities and, to the maximum extent practicable, to avoid disruption, interruption or other adverse effects on traffic flow, throughput or level of service on the Project and Related Transportation Facilities. Developer shall conduct traffic management in accordance with all applicable Technical Provisions, Laws and Governmental Approvals, and in accordance with the Transportation Management Plan and Temporary Traffic Control Plans.
3.3.2 Developer shall prepare and submit to IFA for its approval a Transportation Management Plan for managing traffic. It shall address (a) during the initial construction of the Project, orderly and safe movement and diversion of traffic on Related Transportation Facilities,, (b) throughout the Term after commencement of traffic operations, orderly and safe movement and diversion of traffic on the Project and Related Transportation Facilities, and (c) between Substantial Completion and Final Acceptance, orderly and safe movement and diversion of traffic on the Project and Related Transportation Facilities. Developer shall prepare the Transportation Management Plan in accordance with Section 12.3 and Section 18.2.