Traffic Signal. SC-4.1 "Traffic Signal " shall be measured as lump sum for installing and programming a complete and operational traffic signal system, including traffic signal heads, mast arms and poles, pedestal poles, bases, vehicular detection system, emergency vehicle detection, pedestrian detection, wiring, street lighting and additional appurtenant items and related work necessary for the construction of the improvements to provide a finished product as intended by the Contract Documents. SC-4.2 Payment shall be made at the contract unit price bid as shown in the Bid Form for “Traffic Signal.” Payment shall be full compensation for furnishing and installing all materials and appurtenant work.
Appears in 2 contracts
Sources: Agreement for Public Improvements, Agreement for Public Improvements