Transition to Permanent Premises. 5.03.1 The Authority shall give written notice to the Airline of the estimated Substantial Completion Date of the Airline's Permanent Premises, at least one hundred and twenty (120) days prior to said date. The Airline will be permitted to install its own equipment and furnishings in the Airline's Permanent Premises beginning sixty (60) days prior to such estimated Substantial Completion Date. 5.03.2 The Airline shall move into and occupy its Permanent Premises on or before the actual Substantial Completion Date of such Permanent Premises whereupon such Permanent Premises shall not be considered TAP subject to Section 5.02; provided, however, that if the Airline notifies the Authority as promptly as is reasonably practicable upon receipt of the notice specified in Paragraph 5.03.1 that it cannot reasonably prepare this Permanent Premises by the estimated Substantial Completion Date, and the reasons therefor, the Airline shall have additional time, not to exceed thirty (30) days, to move into and occupy its Permanent Premises. Unless a different payment is required by Section 8.14, the Airline shall be subject to, and shall pay, the rentals, fees, and charges for its Permanent Premises beginning on the actual Substantial Completion Date thereof regardless of whether the Airline occupies its Permanent Premises prior to, on, or after such actual Substantial Completion Date. 5.03.3 If the Airline's Permanent Premises are not completed by the estimated Substantial Completion Date that was contained in the written notice given by the Authority pursuant to Paragraph 5.03.1, the Authority shall not be liable to the Airline for failure to deliver possession or to complete said Permanent Premises by said date. The Authority will notify the Airline of any change in such estimated Substantial Completion Date.
Appears in 2 contracts
Sources: Airport Use Agreement, Lease Agreement
Transition to Permanent Premises. 5.03.1 The Authority shall give written notice to the Airline of the estimated Substantial Completion Date of the Airline's Permanent Premises, at least one hundred and twenty (120) days prior to said date. The Airline will be permitted to install its own equipment and furnishings in the Airline's Permanent Premises beginning sixty (60) days prior to such estimated Substantial Completion Date.
5.03.2 The Airline shall move into and occupy its Permanent Premises on or before the actual Substantial Completion Date of such Permanent Premises whereupon such Permanent Premises shall not be considered TAP subject to Section 5.02; provided, however, that if the Airline notifies the Authority as promptly as is reasonably practicable upon receipt of the notice specified in Paragraph 5.03.1 5.
03.1 that it cannot reasonably prepare this its Permanent Premises by the estimated Substantial Completion Date, and the reasons therefor, the Airline shall have additional time, not to exceed thirty (30) days, to move into and occupy its Permanent Premises. Unless a different payment is required by Section 8.14, the Airline shall be subject to, and shall pay, the rentals, fees, and charges for its Permanent Premises beginning on the actual Substantial Completion Date thereof regardless of whether the Airline occupies its Permanent Premises prior to, on, or after such actual Substantial Completion Date.
5.03.3 If the Airline's Permanent Premises are not completed by the estimated Substantial Completion Date that was contained in the written notice given by the Authority pursuant to Paragraph 5.03.1, the Authority shall not be liable to the Airline for failure to deliver possession or to complete said Permanent Premises by said date. The Authority will notify the Airline of any change in such estimated Substantial Completion Date.