Tree Protection. Before the commencement of Works, a Tree Protection Zone/s (TPZ) must be established around all tree/s to be retained within the site boundary. Tree protection must be maintained in accordance with the AS 4970-2009: Protection of Trees on Development Sites. The tree protection measures and zones offered by the Entrant must be approved by the Land Owners Representative prior to works commencing. Each TPZ must have: • Mulch installed and maintained to a depth of 75mm for the duration of Works; and The following works shall be excluded from within any TPZ: • Soil cut or fill including excavation and trenching; • Soil cultivation, disturbance or compaction; • Stockpiling or storage of bulk materials including soil, gravel, sand or similar materials; • The movement and storage of plant, equipment and vehicles; • The disposal of any toxic liquids including paint, solvents, cement slurry, fuel and oil;