Trial Operation. 42.3.1 After successful completion of Commissioning Tests of the Facility, Contractor shall notify the same to Owner and seek approval of Owner for proceeding with trial operation of the Facility specified in Technical Specification (the “Trial Operation”). Contractor shall proceed with Trial Operation after receipt of approval from Owner. 42.3.2 Minimum duration of Trial Operation shall be 3 (three) days during which Facility including all associated sub-systems and auxiliaries shall be run in integrated manner at rated full load / part load as made available by the Owner. 42.3.3 During Trial Operation, Facility shall necessarily be operated uninterruptedly for at least seventy two (72) hours at its rated full load. 42.3.4 In the event of interruptions to the Trial Operation, for which Contractor is responsible, Trial Operation shall be restarted. 42.3.5 As part of Trial Operation of the Facility, following shall be demonstrated by the Contractor: 42.3.5.1 Sustained capability of the Facility;
Appears in 2 contracts
Sources: Contract for Supply and Installation of New Battery Cells, Contract for Supply and Implementation of Online Monitoring System