Unchanged. The Aggregate Provisional Sum will be (increased) (decreased) (unchanged) by this Change Order in the amount of........................................................................................................................................................... $ Unchanged The new Contract Price including this Change Order will be........................................................................... $ 2,360,000,000 The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary): N/A Adjustment to Payment Schedule: N/A Adjustment to Minimum Acceptance Criteria: N/A Adjustment to Performance Guarantees: N/A Adjustment to Design Basis: N/A Other adjustments to liability or obligation of Contractor or Owner under the Agreement: Select either A or B: [A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ SB Contractor /s/ EL Owner [B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives. /s/ ▇▇ ▇▇▇▇▇▇▇▇ /s/ ▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇▇▇▇▇▇ Owner Contractor ▇▇ ▇▇▇▇▇▇▇▇ ▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇▇▇▇▇▇ Name Name SVP E&C SVP Title Title May 18, 2018 May 18, 2018 Date of Signing Date of Signing PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 CHANGE ORDER NUMBER: CO-00002 DATE OF CHANGE ORDER: May 18, 2018 The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary) 1. Pursuant to Article 6, the Parties have agreed to amend and restate Attachment C - Payment Schedule for Stage 2. 2. The amended and restated Attachment C is attached as Exhibit 1 hereto. The original Contract Price was......................................................................................................................... $ 2,360,000,000 Net change by previously authorized Change Orders (#00001)........................................................................ $ 0.00 The Contract Price prior to this Change Order was........................................................................................... $ 0.00
Appears in 2 contracts
Sources: Change Order (Cheniere Energy Inc), Change Order (Cheniere Corpus Christi Holdings, LLC)
Unchanged. The Aggregate Provisional Sum will be (increased) (decreased) (unchanged) by this Change Order in the amount of........................................................................................................................................................... $ Unchanged The new Contract Price including this Change Order will be........................................................................... $ 2,360,000,000 The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary): N/A Adjustment to Payment Schedule: N/A Yes. See Exhibit 1 of this Change Order. Adjustment to Minimum Acceptance Criteria: N/A Adjustment to Performance Guarantees: N/A Adjustment to Design Basis: N/A Other adjustments to liability or obligation of Contractor or Owner under the Agreement: Select either A or B: [A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ SB Contractor /s/ EL Owner [B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives. /s/ ▇▇ ▇▇▇▇▇▇▇▇ /s/ ▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇▇▇▇▇▇ Owner Contractor ▇▇ ▇▇▇▇▇▇▇▇ ▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇▇▇▇▇▇ Name Name SVP E&C SVP Title Title May 18, 2018 May 18, 2018 Date of Signing Date of Signing PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 CHANGE ORDER NUMBER: CO-00002 CO-00003 DATE OF CHANGE ORDER: May 1824, 2018 The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
1. The Fuel Provisional Sum in Section 1.2 of Attachment EE, Schedule EE-1 of the Agreement prior to this Change Order was Ten Million, Seven Hundred Eighty Four Thousand, Four Hundred Sixty Six U.S. Dollars (U.S. $10,784,466). The Fuel Provisional Sum is hereby decreased by Two Million, Thirty Six Thousand, Six Hundred Two U. S. Dollars (U.S. $2,036,602) and the new value as amended by this Change Order shall be Eight Million, Seven Hundred Forty Seven Thousand, Eight Hundred Sixty Four U.S. Dollars $8,747,864.
2. Pursuant to instructions in Section 1.2 of Attachment EE, Schedule EE-1 of the Agreement, Exhibit 1 to this Change Order illustrates the calculation of the final fuel costs in the Agreement.
3. Schedules C-1 Aggregate Labor and Skills Price Milestone Payment Schedule of Attachment C of the Agreement will be amended by including the milestones listed in Exhibit 2 of this Change Order. The original Contract Price was......................................................................................................................... $ 2,360,000,000 Net change by previously authorized Change Orders (0001-00002)................................................................. $ — The Contract Price prior to this Change Order was........................................................................................... $ 2,360,000,000 The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... $ *** The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... $ *** The new Contract Price including this Change Order will be........................................................................... $ 2,357,963,398 The original Aggregate Equipment Price was................................................................................................... $ *** Net change by previously authorized Change Orders (0001-00002)................................................................. $ *** The Aggregate Equipment Price prior to this Change Order was...................................................................... $ *** The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... $ *** The new Aggregate Equipment Price including this Change Order will be ..................................................... $ *** The original Aggregate Labor and Skills Price was.......................................................................................... $ *** Net change by previously authorized Change Orders (0001-00002)................................................................. $ *** The Aggregate Labor and Skills Price prior to this Change Order was............................................................. $ *** The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... $ *** The new Contract Price including this Change Order will be........................................................................... $ *** The original Aggregate Provisional Sum was.................................................................................................... $ 295,549,906 Net change by previously authorized Change Orders (0001-00002)................................................................. $ — The Aggregate Provisional Sum prior to this Change Order was...................................................................... $ 295,549,906 The Aggregate Provisional Sum will be unchanged by this Change Order in the amount of........................... $ (2,036,602 ) The new Aggregate Provisional Sum including this Change Order will be...................................................... $ 293,513,304 The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary): N/A Adjustment to Payment Schedule: Yes. See Exhibit 2 of this Change Order. Adjustment to Minimum Acceptance Criteria: N/A Adjustment to Performance Guarantees: N/A Adjustment to Design Basis: N/A Other adjustments to liability or obligation of Contractor or Owner under the Agreement: N/A Select either A or B: [A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ SB Contractor /s/ EL Owner [B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives. /s/ ▇▇ ▇▇▇▇▇▇▇▇ /s/ ▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇▇▇▇▇▇ For Owner Contractor ▇▇ ▇▇▇▇▇▇▇▇ ▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇▇▇▇▇▇ Name Name SVP E&C SVP Title Title June 13, 2018 May 24, 2018 Date of Signing Date of Signing PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 CHANGE ORDER NUMBER: CO-00004 DATE OF CHANGE ORDER: May 29, 2018 The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
1. The Currency Provisional Sum in Section 1.1 of Attachment EE, Schedule EE-1 of the Agreement prior to this Change Order was Two Hundred Twelve Million, Four Hundred Fifty Three Thousand, Four Hundred Forty Nine U.S. Dollars (U.S. $212,453,449). The Currency Provisional Sum is hereby increased by Five Hundred Seventy Three Thousand, Seventy One U. S. Dollars (U.S. $573,071) and the new value as amended by this Change Order shall be Two Hundred Thirteen Million, Twenty Six Thousand, Five Hundred Twenty U.S. Dollars (U.S. $213,026,520).
2. Pursuant to instructions in Section 1.1 of Attachment EE, Schedule EE-1 of the Agreement, Exhibit 1 to this Change Order illustrates the calculation of the final currency costs in the Agreement.
3. Schedules C-3 Aggregate Equipment Price Milestone Payment Schedule of Attachment C of the Agreement will be amended by including the milestones listed in Exhibit 2 of this Change Order. The original Contract Price was......................................................................................................................... $ 2,360,000,000 Net change by previously authorized Change Orders (0001-00003)................................................................. $ (2,036,602 ) The Contract Price prior to this Change Order was........................................................................................... $ 2,357,963,398 The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... $ *** The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... $ *** The new Contract Price including this Change Order will be........................................................................... $ 2,358,536,469 The original Aggregate Equipment Price was................................................................................................... $ *** Net change by previously authorized Change Orders (0001-00003)................................................................. $ *** The Aggregate Equipment Price prior to this Change Order was...................................................................... $ *** The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... $ *** The new Aggregate Equipment Price including this Change Order will be ..................................................... $ *** The original Aggregate Labor and Skills Price was.......................................................................................... $ *** Net change by previously authorized Change Orders (0001-00003)................................................................. $ *** The Aggregate Labor and Skills Price prior to this Change Order was............................................................. $ *** The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... $ *** The new Contract Price including this Change Order will be........................................................................... $ *** The original Aggregate Provisional Sum was.................................................................................................... $ 295,549,906 Net change by previously authorized Change Orders (0001-00003)................................................................. $ (2,036,602 ) The Aggregate Provisional Sum prior to this Change Order was...................................................................... $ 293,513,304 The Aggregate Provisional Sum will be unchanged by this Change Order in the amount of........................... $ 573,071 The new Aggregate Provisional Sum including this Change Order will be...................................................... $ 294,086,375 The following dates are modified (list all dates modified; insert N/A if no dates modified): N/A Adjustment to other Changed Criteria (insert N/A if no changes or impact; attach additional documentation if necessary): N/A Adjustment to Payment Schedule: Yes. See Exhibit 2 of this Change Order. Adjustment to Minimum Acceptance Criteria: N/A Adjustment to Performance Guarantees: N/A Adjustment to Design Basis: N/A Other adjustments to liability or obligation of Contractor or Owner under the Agreement: Select either A or B: [A] This Change Order shall constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall be deemed to compensate Contractor fully for such change. Initials: /s/ SB Contractor /s/ EL Owner [B] This Change Order shall not constitute a full and final settlement and accord and satisfaction of all effects of the change reflected in this Change Order upon the Changed Criteria and shall not be deemed to compensate Contractor fully for such change. Initials: Contractor Owner Upon execution of this Change Order by Owner and Contractor, the above-referenced change shall become a valid and binding part of the original Agreement without exception or qualification, unless noted in this Change Order. Except as modified by this and any previously issued Change Orders, all other terms and conditions of the Agreement shall remain in full force and effect. This Change Order is executed by each of the Parties’ duly authorized representatives. /s/ ▇▇ ▇▇▇▇▇▇▇▇ /s/ ▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇▇▇▇▇▇ For Owner Contractor ▇▇ ▇▇▇▇▇▇▇▇ ▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇▇▇▇▇▇ Name Name SVP E&C SVP Title Title June 13, 2018 May 30, 2018 Date of Signing Date of Signing PROJECT NAME: Corpus Christi Stage 2 Liquefaction Facility OWNER: Corpus Christi Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: December 12, 2017 CHANGE ORDER NUMBER: CO-00005 DATE OF CHANGE ORDER: July 10, 2018 The Agreement between the Parties listed above is changed as follows: (attach additional documentation if necessary)
1. Pursuant to Article 66 of the Agreement, the Parties have agreed agree Contractor will implement changes to amend and restate Attachment C - Payment Schedule for Stage 2the trim on the JT valve 13PV-16002, located in the methane cold box of Train 3.
2. The scope of this Change Order is further detailed in Exhibit 1.
3. The cost breakdowns for the scope of work described in this Change Order are detailed in Exhibit 2.
4. Schedules C-1 and C-3 (Milestone Payment Schedules) of Exhibit C of the Agreement will be amended and restated Attachment C is attached as by including the Milestones listed in Exhibit 1 hereto3 of this Change Order. The original Contract Price was......................................................................................................................... $ 2,360,000,000 Net change by previously authorized Change Orders (#000010001-00003)........................................................................ ................................................................. $ 0.00 (1,463,531 ) The Contract Price prior to this Change Order was........................................................................................... $ 0.002,358,536,469 The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... $ *** The Aggregate Labor and Skills Price will be changed by this Change Order in the amount of...................... $ *** The new Contract Price including this Change Order will be........................................................................... $ 2,358,747,493 The original Aggregate Equipment Price was................................................................................................... $ *** Net change by previously authorized Change Orders (0001-00003)................................................................. $ *** The Aggregate Equipment Price prior to this Change Order was...................................................................... $ *** The Aggregate Equipment Price will be changed by this Change Order in the amount of............................... $ *** The new Aggregate Equipment Pr
Appears in 2 contracts
Sources: Change Order (Cheniere Energy Inc), Change Order (Cheniere Corpus Christi Holdings, LLC)