Unilateral Change Order. 100 In the event that agreement cannot be reached as to the cost or credit of the changed work, the Authority shall prepare a cost estimate, and the Contractor will be issued a unilateral change order to proceed with the changed work at a cost not-to-exceed the Authority's estimate. The Contractor shall proceed with the work and maintain accurate records of the actual cost of labor and material to perform the work.
Appears in 3 contracts
Sources: Standard Form of Agreement for Facilities Projects, Standard Form of Agreement for Facilities Projects, Standard Form of Agreement for Facilities Projects