Unilateral extensions. (a) Subject to Clause 12.4(b), the State may, by notice to the Operator, unilaterally extend any Date for Completion where the State considers that any act or omission of the State or a State Associate will, or is likely to, delay the Date for Completion. (b) The State is not required to exercise the State’s discretion in accordance with Clause 12.4(a) for the benefit of the Operator or at all. (c) The exercise or failure to exercise the State’s discretion in accordance with this Clause 12.4 is not capable of being the subject of a Dispute in accordance with Clause 34 or otherwise subject to review.
Appears in 2 contracts
Sources: Perth Stadium Project Operator Agreement, Perth Stadium Project Operator Agreement