Unit Price Work. The unit price of an item of Unit Price Work shall be subject to re-evaluation and adjustment pursuant to a requested Change Order under the following conditions: (1) If the total cost of a particular item of Unit Price Work amounts to 5% or more of the Contract Sum and the variation in the quantity of the particular item of Unit Price Work performed by Contractor differs by more than 15% from the estimated quantity of such item indicated in the Agreement; and (2) If there is no corresponding adjustment with respect to any other item of Work; and (3) If Contractor believes that it has incurred additional expense as a result thereof; or (4) If Owner believes that the quantity variation entitles it to an adjustment in the unit price; or (5) If the parties are unable to agree as to the effect of any such variations in the quantity of Unit Price Work performed.
Appears in 3 contracts
Sources: Construction Agreement, Construction Agreement, Construction Agreement
Unit Price Work. The unit price of an item of Unit Price Work shall be subject to re-evaluation and adjustment pursuant to a requested Change Order under the following conditions:
(1) If the total cost of a particular item of Unit Price Work amounts to 5% or more of the Contract Sum and the variation in the quantity of the particular item of Unit Price Work performed by Contractor differs by more than 15% from the estimated quantity of such item indicated in the Agreement; and
(2) If there is no corresponding adjustment with respect to any other item of Work; and
(3i) If Contractor believes that it has incurred additional expense as a result thereof; or
(4ii) If Owner believes that the quantity variation entitles it to an adjustment in the unit price; or
(5iii) If the parties are unable to agree as to the effect of any such variations in the quantity of Unit Price Work performed.