Common use of Unit Priced Change Orders Clause in Contracts

Unit Priced Change Orders. Unit prices shall be deemed to include all costs for labor, material, overhead and profit, and shall not be subject to change regardless of any change in the estimated quantities. Unit-priced Change Orders shall initially include an estimated increase in the Maintenance Price based on estimated quantities. Upon final determination of the quantities, ▇▇▇▇▇ will issue a modified Change Order setting forth the final adjustment to the Maintenance Price.

Appears in 25 contracts

Sources: Capital Maintenance Agreement, Capital Maintenance Agreement, Capital Maintenance Agreement

Unit Priced Change Orders. Unit prices shall be deemed to include all costs for labor, material, overhead and profit, and shall not be subject to change regardless of any change in the estimated quantities. Unit-priced Change Orders shall initially include an estimated increase in the Maintenance Price based on estimated quantities. Upon final determination of the quantities, ▇▇▇▇▇ TxDOT will issue a modified Change Order setting forth the final adjustment to the Maintenance Price.

Appears in 23 contracts

Sources: Capital Maintenance Agreement, Capital Maintenance Agreement, Capital Maintenance Agreement

Unit Priced Change Orders. Unit prices shall be deemed to include all costs for labor, material, overhead and profit, and shall not be subject to change regardless of any change in the estimated quantities. Unit-priced Change Orders shall initially include an estimated increase in the Maintenance Price based on estimated quantities. Upon final determination of the quantities, ▇▇▇▇▇ will issue a modified Change Order setting forth the final adjustment to the Maintenance Price.

Appears in 4 contracts

Sources: Design Build Agreement, Design Build Contract, Design Build Contract

Unit Priced Change Orders. Unit prices shall be deemed to include all costs for labor, material, overhead and profit, and shall not be subject to change regardless of any change in the estimated quantities. Unit-priced Change Orders shall initially include an estimated increase in the Maintenance Price based on estimated quantities. Upon final determination of the quantities, ▇▇▇▇▇ TxDOT will issue a modified Change Order setting forth the final adjustment to the Maintenance Price, which shall not exceed the stated not-to-exceed amount.

Appears in 4 contracts

Sources: Capital Maintenance Agreement, Capital Maintenance Agreement, Capital Maintenance Agreement

Unit Priced Change Orders. Unit prices shall be deemed to include all costs for labor, material, overhead and profit, and shall not be subject to change regardless of any change in the estimated quantities. Unit-priced Change Orders shall initially include an estimated increase in the Maintenance Price based on estimated quantities. Upon final determination of the quantities, ▇▇▇▇▇ TxDOT will issue a modified Change Order setting forth the final adjustment to the Maintenance Price.

Appears in 3 contracts

Sources: Design Build Contract, Design Build Agreement, Design Build Agreement

Unit Priced Change Orders. Unit prices shall be deemed to include all costs for labor, material, overhead and profit, and shall not be subject to change regardless of any change in the estimated quantities. Unit-priced Change Orders shall initially include an estimated increase in the Maintenance applicable Price based on estimated quantities. Upon final determination of the quantities, ▇▇▇▇▇ TxDOT will issue a modified Change Order setting forth the final adjustment to the Maintenance applicable Price.

Appears in 1 contract

Sources: Statewide Toll System Integration and Maintenance Agreement