Common use of Use of Recycled Materials Clause in Contracts

Use of Recycled Materials. The Contractor shall prepare and demonstrate compliance with a spoil plan and a waste minimisation plan. The spoil plan shall be based upon the recommendations of ▇▇▇▇▇ Report 179:1997. Where possible the contractor should look to use reclaimed local stone for the visible faces of the fish pass. However the use of reclaimed stone should not occur where it is more expensive than using new stone, or if there is a risk of contamination. Samples of the stone shall be provided/shown to the employer prior to commencement of construction.

Appears in 2 contracts

Sources: Construction Contract, Construction Contract