Common use of Utility Relocation Clause in Contracts

Utility Relocation. County shall comply with Government Code section 4215, regarding responsibility for the removal, relocation, or protection of existing main or trunk-line utility facilities located on the work site, if such utilities are not identified by the County in the Contract Documents. County shall compensate Contractor for the costs of locating, repairing damage not due to the failure of the contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the Contract Documents with reasonable accuracy, and for equipment on the work site necessarily idled during such work. Contractor shall not be assessed liquidated damages for delay in completion of the work, when such delay was caused by the failure of County or the owner of the utility to provide for removal or relocation of such utility facilities.

Appears in 2 contracts

Sources: Aggregate Public Works Construction Contract, Aggregate Public Works Construction Contract

Utility Relocation. County shall comply with Government Code section 4215, regarding responsibility for the removal, relocation, or protection of existing main or trunk-line utility facilities located on the work Project site, if such utilities are not identified by the County in the Contract Documents. County shall compensate Contractor for the costs of locating, repairing damage not due to the failure of the contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the Contract Documents with reasonable accuracy, and for equipment on the work Project site necessarily idled during such work. Contractor shall not be assessed liquidated damages for delay in completion of the workProject, when such delay was caused by the failure of County or the owner of the utility to provide for removal or relocation of such utility facilities.

Appears in 1 contract

Sources: Public Works Construction Contract

Utility Relocation. County shall comply with Government Code section 4215, regarding responsibility for the removal, relocation, or protection of existing main or trunk-line utility facilities located on the work Project site, if such utilities are not identified by the County in the Contract Documents. County shall compensate Contractor for the costs of locating, repairing damage not due to the failure of the contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the Contract Documents with reasonable accuracy, and for equipment on the work site Project necessarily idled during such work. Contractor shall not be assessed liquidated damages for delay in completion of the work, Project when such delay was caused by the failure of County or the owner of the utility to provide for removal or relocation of such utility facilities.

Appears in 1 contract

Sources: Aggregate Public Works Construction Contract

Utility Relocation. County shall comply with Government Code section 4215, regarding responsibility for the removal, relocation, or protection of existing main or trunk-line utility facilities located on the work Project site, if such utilities are not identified by the County in the Contract Documents. County shall compensate Contractor for the costs of locating, repairing damage not due to the failure of the contractor to exercise reasonable care, and removing or relocating such utility facilities not indicated in the Contract Documents with reasonable accuracy, and for equipment on the work site Project necessarily idled during such work. Contractor shall not be assessed liquidated damages for delay in completion of the workProject, when such delay was caused by the failure of County or the owner of the utility to provide for removal or relocation of such utility facilities.

Appears in 1 contract

Sources: Personal Services Agreement