Common use of Weather Delay Clause in Contracts

Weather Delay. The term "Weather Delay" shall mean, as to the Complex and respectively as to each Building, as applicable, the period of delay in the Substantial Completion of construction of the applicable Improvements occasioned by any abnormally adverse weather conditions (compared to the average seasonal weather conditions experienced in Mountain View, California during the relevant period of construction) in the nature of abnormal rains (and any resultant flooding) such as might occur due to an el nino, provided that there shall not be considered to be any Weather Delay unless the aggregate affect of all Weather Delays (excluding average seasonal weather conditions) are reasonably estimated to have delayed the Substantial Completion of the respective Improvements by a period in excess of thirty (30) calendar days where such days of delay are attributable solely to a Weather Delay.

Appears in 2 contracts

Sources: Construction Agreement (Alza Corp), Construction Agreement (Alza Corp)