Whenever necessary. due to receipt of a high volume of simultaneous submittals, the Designer shall notify the Contractor that submittal review must be prioritized and request the Contractor to provide said prioritization, in writing, of those simultaneous submittals based on the contractor’s approved project schedule. This shall have the effect of staying the twenty-one day review requirement for the lower priority submittals.
Appears in 2 contracts
Sources: Standard Articles of Agreement Between Owner & Designer, Design Services Agreement