Withholding Progress Payments. The Public Owner may withhold all or part of any progress payment or payments until the Prime Contractor or Subcontractor has remedied the breach of this Agreement. In the event that progress payments are withheld, the Prime Contractor or Subcontractor shall not be entitled to interest on said payments. If a Subcontractor is responsible for noncompliance of the workforce Program requirements, the Public Owner may choose to withhold only the Subcontractor’s portion of the progress payment.