WORK DONE CERTIFICATE. 14.1. On satisfactory completion of work, WDC shall be prepared on monthly basis by the contractor within 02 days from the date of completion of tasks and shall be certified by the concerned OIC of user Department (not below the rank of Chief Manager). The WCC shall accompany the related Log Sheets/Service Report etc. 14.2. WDC shall be certified & issued post completion of the individual activities 14.3. Payment shall be as per the quantities certified in WDC. 14.4. The WDC shall include cumulative statement of jobs carried out till last WDC. The necessary service entry shall be made in SAP system by the WDC certifying authority & will be submitted to the contractor for further invoicing. The WDC shall bear relevant Service Entry sheet no., PO no. and respective item Sr. No., sub service line item of the PO. 14.5. The WDC must clearly mention the scheduled dates for starting & completion/delivery of the jobs as mutually agreed between OIC MDL & contractor and the actual dates of start & completion. 14.6. In case of delays, the duration along with numbers of delayed days shall be specified in respective WDCs to invoke LD clause and effect recoveries from sub contractor's invoice. 14.7. An illustrative format of Work Done Certificate is at Annexure- I.
Appears in 3 contracts
Sources: Service Level Agreement (Sla), Outsourcing Agreements, Additional Service Level Agreement (Asla)
WORK DONE CERTIFICATE. 14.115.1. On satisfactory completion of work, WDC shall be prepared on monthly basis by the contractor within 02 days from the date of completion of tasks and shall be certified by the concerned OIC of user Department (not below the rank of Chief Manager). The WCC shall accompany the related Log Sheets/Service Report etc.
14.215.2. WDC shall be certified & issued post completion of the individual activities.
14.315.3. Payment shall be as per the quantities certified in WDC.
14.415.4. The WDC shall include cumulative statement of jobs carried out till last WDC. The necessary service entry shall be made in SAP system by the WDC certifying authority & will be submitted to the contractor for further invoicing. The WDC shall bear relevant Service Entry sheet no., PO no. and respective item Sr. No., sub service line item of the PO.
14.515.5. The WDC must clearly mention the scheduled dates for starting & completion/delivery of the jobs as mutually agreed between OIC MDL & contractor and the actual dates of start & completion.
14.615.6. In case of delays, the duration along with numbers of delayed days shall be specified in respective WDCs to invoke LD clause and effect recoveries from sub contractor's invoice.
14.715.7. An illustrative format of Work Done Certificate is at Annexure- I.
Appears in 2 contracts
Sources: Additional Service Level Agreement (Sla), Additional Service Level Agreement (Sla)
WORK DONE CERTIFICATE. 14.1. On satisfactory completion of work, WDC shall be prepared on monthly basis by the contractor within 02 days from the date of completion of tasks and shall be certified by the concerned OIC of the user Department (not below the rank of Chief Managermanager). The WCC shall accompany the related Log Sheets/Service Report etc.
14.2. WDC shall be certified & issued post completion of the individual activities
14.3. Payment shall be made as per the quantities certified in WDC.
14.414.2. The WDC shall include cumulative statement of jobs carried out till last WDC. The necessary service entry shall be made in SAP system by the WDC certifying authority & will be submitted to the contractor for further invoicing. The WDC shall bear relevant Service Entry sheet no., PO no. and respective item Sr. No., sub service line item of the PO.
14.514.3. The WDC must clearly mention the scheduled dates for starting & completion/delivery of the jobs work as mutually agreed between OIC MDL & contractor and the actual dates of start & completion.
14.6▇▇.▇. In ▇▇ case of delays, the duration along with numbers of delayed days shall be specified in respective WDCs to invoke LD clause and effect recoveries from sub contractor's invoice.
14.714.5. The successful Bidder (Contractor) would have to submit WDC as per the then prevailing format, at the time of order placement. The same would be made available at appropriate time. An illustrative Illustrative format of Work Done Certificate work done certificate is placed at Annexure- Annexure I.
Appears in 1 contract
WORK DONE CERTIFICATE. 14.1. On satisfactory completion of work, WDC shall be prepared on monthly basis by the contractor within 02 days from the date of completion of tasks and shall be certified by the concerned OIC of user Department (not below the rank of Chief Manager). The WCC shall accompany the related Log Sheets/Service Report etc.
14.2. WDC shall be certified & issued post completion of the individual activities.
14.3. Payment shall be as per the quantities certified in WDC.
14.4. The WDC shall include cumulative statement of jobs carried out till last WDC. The necessary service entry shall be made in SAP system by the WDC certifying authority & will be submitted to the contractor for further invoicing. The WDC shall bear relevant Service Entry sheet no., PO no. and respective item Sr. No., sub service line item of the PO.
14.5. The WDC must clearly mention the scheduled dates for starting & completion/delivery of the jobs as mutually agreed between OIC MDL & contractor and the actual dates of start & completion.
14.6. In case of delays, the duration along with numbers of delayed days shall be specified in respective WDCs to invoke LD clause and effect recoveries from sub contractor's invoice.
14.7. An illustrative format of Work Done Certificate is at Annexure- I.
Appears in 1 contract
WORK DONE CERTIFICATE. 14.1. On satisfactory completion of work, WDC shall be prepared on monthly basis by the contractor within 02 days from the date of completion of tasks and shall be certified by the SM/concerned OIC of user Department (not below the rank of Chief Manager). The WCC shall accompany the related Log Sheets/Service Report etc.
14.2. WDC shall be certified & issued post completion of the individual activities
14.3. Payment shall be made as per the quantities certified in WDC.
14.414.2. The WDC shall include cumulative statement of jobs carried out till last WDC. The necessary service entry shall be made in SAP system by the WDC certifying authority & will be submitted to the contractor for further invoicing. The WDC shall bear relevant Service Entry sheet no., PO no. and respective item Sr. No., sub service line item of the PO.
14.5. The WDC must clearly mention the scheduled dates for starting & completion/delivery of the jobs as mutually agreed between OIC MDL User Dept. & contractor and the actual dates of start & completion. WDC will be signed after completion of hot riveting work cleared by Inspection authority. Sequence for cleaning of tanks will be given by berth Executive.
14.614.3. The necessary service entry shall be made in SAP system by the WDC authority & WDC/WCC will be submitted to the contractor for further invoicing. The WDC/WCC shall bear relevant Service Entry Sheet No., PO No. and respective item Sr. No., sub service line item of the PO.
14.4. In case of delays, the duration along with numbers of delayed days shall be specified in respective WDCs WDCs/WCCs to invoke LD clause Clause and effect recoveries from sub contractor's invoice.
14.7. An illustrative format of Work Done Certificate is placed at Annexure- I.Annexure IV.
Appears in 1 contract
WORK DONE CERTIFICATE. 14.1. On satisfactory completion of work, WDC Work Completion Certificate shall be prepared on monthly basis issued by the contractor within 02 days from the date of completion of tasks and shall be certified by the concerned OIC of user Department (not below the rank of Chief Manager). The WCC shall accompany Manager and also duly endorsed by Ship Manager (SM) of Yard 12652 separately indicating details of the related Generator along with 15 Days Log Sheets/Service Report etcSheet.
14.2. WDC Work Completion certificate (WCC) shall be certified & issued post on Satisfactory completion of respective work with inspection and acceptance reports. Department responsible to issue WCC shall be Planning/User dept. (Chief Manager and above) whoever is availing the individual activitiessaid services.
14.3. Payment shall be as per the quantities certified in WDC.
14.4. The WDC shall include cumulative statement of jobs carried out till last WDC. The necessary service entry shall be made in SAP system by the WDC certifying authority & and will be submitted to the contractor for further invoicing. The WDC shall bear relevant Service Entry sheet noSheet No., PO noNo. and respective item Sr. No., sub service line item of the PO.
14.514.4. The WDC must clearly mention the scheduled dates for starting & completion/delivery of the jobs as mutually agreed between OIC MDL & contractor completion schedule and the actual dates of work done schedule for start & completiondate and end date.
14.614.5. In case of delays, the duration along with numbers of delayed days shall be specified in respective WDCs to invoke LD clause and effect recoveries from sub contractor's ’s invoice.
14.714.6. An illustrative format of Work Done Certificate is at Annexure- I.The successful Bidder/s (Contractor/s) shall submit WDC as per the format.
Appears in 1 contract
Sources: Service Level Agreement (Sla)
WORK DONE CERTIFICATE. 14.1. On satisfactory completion of work, WDC shall be prepared on monthly basis by the contractor within 02 days from the date of completion of tasks and shall be certified by the concerned OIC of user Department (not below the rank of Chief Manager). The WCC shall accompany the related Log Sheets/Service Report etc.be
14.2. WDC shall be certified & issued post completion of the individual activities
14.3. Payment shall be as per the quantities certified in WDC.
14.4. The WDC shall include cumulative statement of jobs carried out till last WDC. The necessary service entry shall be made in SAP system by the WDC certifying authority & will be submitted to the contractor for further invoicing. The WDC shall bear relevant Service Entry sheet no., PO no. and respective item Sr. No., sub service line item of the PO.
14.5. The WDC must clearly mention the scheduled dates for starting & completion/completion/ delivery of the jobs as mutually agreed between OIC MDL & contractor and the actual dates of start & completion.
14.6. In case of delays, the duration along with numbers of delayed days shall be specified in respective WDCs to invoke LD clause and effect recoveries from sub contractor's invoice.
14.7. An illustrative format of Work Done Certificate is at Annexure- I.
Appears in 1 contract
Sources: Service Level Agreement (Sla)
WORK DONE CERTIFICATE. 14.116.1. On satisfactory completion of work, WDC shall be prepared on monthly basis by the contractor within 02 days from the date of completion of tasks and shall be certified by the concerned OIC executive of user Department (not below the rank of Chief Manager). The WCC shall accompany the related Log Sheets/Service Report Sheets/ copy of Attendance Sheets etc.
14.216.2. WDC shall be certified & issued post completion of the individual activities.
14.316.3. Payment shall be as per the quantities certified in WDC.
14.416.4. The WDC shall include cumulative statement of jobs carried out till last WDC. The necessary service entry shall be made in SAP system by the WDC certifying authority & will be submitted to the contractor for further invoicing. The WDC shall bear relevant Service Entry sheet no., PO no. and respective item Sr. No., sub service line item of the PO.
14.516.5. The WDC must clearly mention the scheduled dates for starting & completion/delivery of the jobs as mutually agreed between OIC MDL & contractor and the actual dates of start & completion.
14.616.6. In case of delays, the duration along with numbers of delayed days shall be specified in respective WDCs to invoke LD clause and effect recoveries from sub contractor's invoice.
14.7. An illustrative format of Work Done Certificate is at Annexure- I.