Work modifications. Customer may, by written request to NorthWestern, at any time during the Term of this Agreement and without invalidating the Agreement, request changes to the general scope of the Work. NorthWestern may accept or reject any request for changes. If the change increases or decreases the cost of or time for performing the Work, the parties shall make an equitable adjustment in the payment to NorthWestern and/or the anticipated completion date. Any adjustment to the funding requirement will be based on the reasonable expenditures or savings realized in performing the Work, and shall be based on actual costs. All mutually agreed changes in the Work will be authorized using the form attached as Exhibit 4.
Appears in 2 contracts
Sources: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement