Work Programmes. a The Concessionaire shall prepare and submit a Project Implementation Schedule to the Authority before the Compliance Date. The programme shall include the following: i The order in which the Concessionaire proposes to carry out the development (including each stage of design, procurement, manufacture, delivery to Project Site, erection, testing and commissioning).