ContractTransmission Service Agreement • June 7th, 2024
Contract Type FiledJune 7th, 2024(Transmission Customer), under the terms of PNM’s Open Access Transmission Tariff. The agreement is for 27 MW of reserved transmission capacity (and certain ancillary services) from the San Juan Generating Station 345kV Switchyard to the Luna 345kV Switching Station and represents the Transmission Customer’s exercise of its Right of First Refusal to extend service under a predecessor (now expired) agreement for one year (through calendar year 2003). PNM requests January 1, 2003, as the effective date for each agreement. PNM’s filing is available for public inspection at its offices in Albuquerque, New Mexico.