Common Contracts

1 similar Impact Fee Agreement contracts

BCC MEETING DATE
Impact Fee Agreement • April 8th, 2025

The proposed Road Impact Fee Credit Agreement with 210 East, LLC seeks to establish road impact fee credit for the CR 210 Commercial project for dedication of right-of-way (ROW) on the south side of CR 210 and redesign costs/median modification at the west end of the CR 210 6-laning project that is currently under construction by the County. The approximate 25' strip of right-of-way along the project's CR 210 frontage (.35 acres) is valued by appraisal at $440,000. In addition, a portion of the redesign/median modification cost is proposed for credit in the amount of $75,080 that was determined to be required while the commercial project was in review due to the location of the commercial project at the west end of the 6-laning project under construction. The total road impact fee credit requested is $515,080.00.The impact fee credit will be awarded after the ROW has been dedicated and/or improvements within County ROW have been bonded, as applicable.