Anticipated Project Completion Date definition

Anticipated Project Completion Date. The date six (6) months after the Anticipated Physical Completion Date.
Anticipated Project Completion Date means the later of:
Anticipated Project Completion Date. October 31, 2011.

Examples of Anticipated Project Completion Date in a sentence

  • Anticipated Project Completion Date the date on which the Project Completion Date is forecast to occur as advised to the Agent in the most recent Project Status Certificate and, if requested by the Agent, confirmed by the Independent Technical Consultant.


More Definitions of Anticipated Project Completion Date

Anticipated Project Completion Date means, subject to the occurrence of force majeure or other events beyond the reasonable control of the Authority, the estimated date of completion of the construction of the Project, which shall be December 31, 2020.

Related to Anticipated Project Completion Date

  • Project Completion Date means the date on which the Completion Certificate is issued;

  • project completion period means the period of sixty (60) months commencing from and expiring on for the construction and obtaining of Temporary Occupation Permit or Permits for the whole of the Development as provided in clause 3.3;

  • Project Completion means the date, as determined by the Division after consultation with the Recipient, that operation of the Project is initiated or is capable of being initiated, whichever comes first.

  • Target Completion Date has the meaning given such term in Section 3.3(b).

  • Completion Date means the date of completion of the Services by the Service Provider as certified by the Procuring Entity