Application and Certificate for Payment definition
Examples of Application and Certificate for Payment in a sentence
Based on Project Site observation, the Design Professional shall review the Contractor’s Application for Payment and determine the amount owed to the Contractor and shall certify to the Owner the Contractor's Application and Certificate for Payment.
Based on project site observation, the Design Professional shall review the CM/GC’s Application for Payment and determine the amount owed to the CM/GC and shall certify the CM/GC's Application and Certificate for Payment.
This data shall be attached to the Application and Certificate for Payment (AIA Document G702).
If at the time CMR requests Final Payment there are claims pending which were submitted in strict compliance with the claims submission requirements of the Contract Documents, the Owner may pay undisputed portions of the Final Application and Certificate for Payment as if it were an Application and Certificate for Partial Payment.
The Certificate for Payment shall be issued on the current version of AIA Form G702 (Application and Certificate for Payment) as approved by the Owner.
The forms to be utilized shall be the Owner’s established Application and Certificate for Payment and related Continuation Sheet.
Prime Contractor's Application for Payment shall be filed on the current version of AIA Form G702 (Application and Certificate for Payment), as approved by the Owner.
The performance measure documenting satisfactory completion of Deliverables will be a completed Application and Certificate for Payment (AIA Document G702) and Schedule of Contract Values (AIA Document G703), or its equivalent (see Appendix 1), showing at least 30% of the project completed.
Such Application and Certificate for Payment as approved by the Owner’s Representative will authorize payment by the Owner in an amount equal to the value of the Work completed less any sums retained or deducted by the Owner under the terms of the Contract Documents, and less retainage of five (5) percent of payments approved.
The performance measure documenting satisfactory completion of Deliverables will be a completed Application and Certificate for Payment (AIA Document G702), Schedule of Contract Values (AIA Document G703), and a Certificate of Substantial Completion (AIA Document G704), or its equivalent (see Appendix 1), showing 100% of the project completed, including all retainage amounts paid.