Cluster Restudy definition
Examples of Cluster Restudy in a sentence
Interconnection Study - Any of the following studies: the Cluster Study, the Cluster Restudy, the Surplus Interconnection Service study, the Interconnection Facilities Study, the Affected System Study, the Operational Interconnection Study, and a Material Modification assessment, described in the LGIP.
The results of the Cluster Restudy shall be combined into a single report (Cluster Restudy Report).
Transmission Provider shall complete the Cluster Restudy within one hundred fifty (150) Calendar Days of Transmission Provider informing Interconnection Customers in the Cluster that restudy is needed.
Upon the completion of Transmission Provider’s Cluster Restudy, Transmission Provider will notify Affected System Operator of a potential Affected System impact caused by an Interconnection Request within ten (10) Business Days of the completion of the Cluster Restudy, regardless of whether that potential Affected System impact was previously identified.
If an Interconnection Customer withdraws or is deemed withdrawn pursuant to Section 3.7 of this LGIP during the Interconnection Facilities Study, or after other Interconnection Customers in the same Cluster have executed LGIAs, or requested that unexecuted LGIAs be filed, and Transmission Provider determines a Cluster Restudy is necessary, the Cluster shall be restudied.
The scope of any Cluster Re-study shall be consistent with the scope of an initial Cluster Study pursuant to Article 7.3. Transmission Provider shall use Reasonable Efforts to complete the Cluster Re-Study for all Cluster Areas within one hundred fifty (150) Calendar Days of the commencement of the first Cluster Area Re-Study.
If Transmission Provider decides to delay the Affected System Study, it is not required to meet its obligations under Section 9 of this LGIP until the time that it receives notification from the host transmission provider that the Cluster Restudy is complete.
When Transmission Provider receives initial notification either following the Cluster Study or a Cluster Restudy that an Affected System Interconnection Customer’s proposed interconnection to its host transmission provider may impact Transmission Provider’s Transmission System, Transmission Provider must respond in writing within twenty (20) Business Days whether it intends to conduct an Affected System Study.
Within five (5) Business Days following Transmission Provider notifying each Interconnection Customer within the Cluster that no further Cluster Restudy is required (per Section 7.5 of this LGIP), Transmission Provider shall provide to Interconnection Customer an Interconnection Facilities Study Agreement in the form of Appendix 3 to this LGIP.
Transmission Provider must pay the penalty for each late Cluster Study, Cluster Restudy, and Interconnection Facilities Study on a pro rata basis per Interconnection Request to all Interconnection Customer(s) included in the relevant study that did not withdraw, or were not deemed withdrawn, from Transmission Provider’s interconnection queue before the missed study deadline, in proportion to each Interconnection Customer’s final study cost.