Completion of Unloading definition

Completion of Unloading means, following the Unloading of an LNG Tanker, the situation where all LNG discharge and return lines have been disconnected and such LNG Tanker has been cleared by the Operating Company for departure. [“Completamento della Discarica” in the Italian text]
Completion of Unloading means the time (after the unloading of the LNG Ship or, in the case of Clauses 7.16, 7.18, 7.20 and 7.22 only, after the unloading of the LNG Ship or a failure to unload the LNG Ship) at which LNG unloading and vapor return lines have been finally disconnected at the Discharge Port (or, if the LNG Ship has not been connected to the LNG unloading and vapor return lines at the Discharge Port, at the time at which the failure to deliver or take (as applicable) the relevant LNG Cargo arises);
Completion of Unloading means, in respect of a DES delivery, the disconnection of the flange coupling of the cargo manifold of an LNG Vessel from the flange coupling on the unloading line at Buyer’s Facilities following unloading of the LNG Vessel and completion of final gauging.

Examples of Completion of Unloading in a sentence

  • Seller shall, within forty-eight (48) hours following Completion of Unloading, notify Buyer of the volume of LNG unloaded.

  • Buyer shall, within forty-eight (48) hours following Completion of Unloading, notify Seller or cause Seller to be notified of the quality of the LNG unloaded from the LNG Ship by provision of a written notice, the form of which is to be agreed by the Parties.

  • If the crossover lines are liquid filled (cold) when measurement is taken before unloading commences, they will remain full (cold) until measurement is taken following the Completion of Unloading.

  • If the Quantity Delivered and/or the Price in respect of an LNG Cargo is not capable of being finally determined in accordance with Clause 10.3 promptly following Completion of Unloading in respect of such LNG Cargo, Seller shall provide Buyer with a preliminary invoice as soon as practicable after Completion of Unloading.

  • If the LNG Carrier's manifold and crossover lines are empty (warm) when measurement is taken before unloading commences, they will be emptied prior to measurement following the Completion of Unloading.

  • Seller shall, on a reasonable efforts basis, furnish to Buyer by e-mail or facsimile an invoice within seven (7) days after Completion of Unloading stating the amount of the Contract Price.

  • Buyer shall, on a reasonable efforts basis within twenty-four (24) hours but in no event later than forty-eight (48) hours after Completion of Unloading, complete a laboratory analysis and calculations to determine the quality and BTU content of the LNG unloaded, in accordance with the provisions of Annex I, and shall promptly furnish to Seller or its representative a copy of the laboratory analysis with respect thereto.

  • Used Laytime shall however recommence two (2) hours after Completion of Unloading if the LNG Vessel is delayed in its departure due to Buyer's purposes and shall continue until the termination of such delay.

  • For purposes hereof, the “Initial Gas Day” shall mean the first Gas Day that commences after the expiration of the twenty four (24) hour period immediately following the Completion of Unloading.

  • Notwithstanding that the point of sale, purchase and title transfer for the LNG is as provided in Section 9, the quantity of LNG delivered, sold and purchased shall be determined immediately after Completion of Loading, in the case of an FOB delivery, or Completion of Unloading, in the case of a DES delivery, of each LNG Vessel.


More Definitions of Completion of Unloading

Completion of Unloading means, following the Unloading of an LNG Tanker, the situation where all LNG discharge and return lines have been disconnected and such LNG Tanker has been cleared by the Operating Company for departure. For the purposes of applying the Laytime and Demurrage Time referred to in paragraph IV.3.8, the completion of the discharge must be understood as the disconnection of all LNG unloading and return lines. [“Completamento della Discarica” in the Italian text]
Completion of Unloading means the time (after the unloading of the relevant Cargo at the Receiving Facilities) at which the last transfer pump has been stopped, the liquid manifolds closed so as to prevent any further LNG transfer taking place and the LNG unloading and vapour return lines have been fully disconnected.

Related to Completion of Unloading

  • Completion of work means completion of the entire contracted work. Exhaustion of quantity of any particular item mentioned in the bid document shall not imply completion of work or any component thereof.

  • construction site means a workplace where construction work is being performed;

  • Construction Plant means appliances, machinery with necessary supply to up keep and maintenance of the works or temporary works but dose not include materials or other things intended to form part of the permanent work.