Date of Completion of the Works definition

Date of Completion of the Works means the date certified as such in the Completion Certificate in accordance with Clause 5.21.3 [Completion of Works].
Date of Completion of the Works means the date certified as such in the CompletionCertificate in accordance with Clause 22.1.
Date of Completion of the Works means the date certified as such in the

Examples of Date of Completion of the Works in a sentence

  • If the Date of Completion of the Works or a Stage has not occurred by the Date for Completion for the Works or the Stage, the Contractor must pay liquidated damages at the rate specified in the Contract Particulars for every day after the Date for Completion until the Date of Completion or the Contract is terminated, whichever is first.

  • The Contractor shall execute and complete the WUC at its cost in a proper and workmanlike manner and to a standard consistent with best industry practice and in accordance with the Contract and Contract Documents and shall be solely liable for the care of the Works, temporary works, materials and constructional plant until the Date of Completion of the Works in their entirety.

  • The period which commences on the Date of Completion of the Works or a Stage and which continues for the period specified in the Contract Particulars, as extended by clause 9.11.

  • The period which commences on the Date of Completion of the Works or a Stage and which continues for the period specified in the Contract Particulars, as may be extended under clause 9.11.

  • The Contractor must maintain the insurance policy referred to in clause 7.1.1 until the Date of Completion of the Works in their entirety and must maintain the insurance policy referred to in clause 7.1.2 until the end of the Defects Liability Period.

  • The Contractor must maintain the insurance policy referred to in clause 7.1.1. until the Date of Completion of the Works in their entirety and must maintain the insurance policy referred to in clause 7.1.2. until the end of the Defects Liability Period.

  • The period which commences on the Date of Completion of the Works or a Stage and which continues for the period specified in the Contract Particulars, as may be extended by clause 9.11.

  • Delay Damages shall be the amount stated in the Contract Data, which shall be paid for every day which shall elapse between the relevant Time for Completion and the relevant Date of Completion of the Works or Section.

  • At any time during: the Planning Phase; or the Delivery Phase prior to the Date of Completion of the Works or a Stage (but without limiting clauses 5.3 and 9.6), the Contract Administrator may issue a document titled "Variation Price Request" to the Contractor which will set out details of a proposed Variation which the Commonwealth is considering.

  • The Completion Date is the Date of Completion of the Works as certified by the Employer in accordance with Sub Clause 46.1. The Contract is the Contract between the Employer and the Contractor to execute, complete and maintain the Works.


More Definitions of Date of Completion of the Works

Date of Completion of the Works. April 2, 2008, and as shall be updated, if at all, from time to time, in accordance with the provisions of this Contract.
Date of Completion of the Works means the date certified as such in the Completion Certificate in accordance with SSC, Annexure-IV.

Related to Date of Completion of the Works

  • Date of Completion with respect to a Project shall mean: (i) the date upon which such Project and all components thereof have been acquired or constructed and are capable of performing the functions for which they were intended, as evidenced by an Engineers’ Certificate filed with the Trustee and the Issuer; or (ii) the date on which the Issuer determines, upon the recommendation of or in consultation with the Consulting Engineer, that it cannot complete such Project in a sound and economical manner within a reasonable period of time as evidenced by an Engineers’ Certificate filed with the Trustee and the Issuer; provided that in each case such certificate of the Consulting Engineer shall set forth the amount of all Costs of such Project which have theretofore been incurred, but which on the Date of Completion is or will be unpaid or unreimbursed.

  • Date of commencement of the project means the date of the agreement.

  • Construction Completion Date or “Completion Date” means the date by which the overall Development of the Project is completed in accordance with the provisions of this Agreement and when the Completion Certificate is issued by the Authority as per Article 14.1.

  • The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.

  • Substantial Completion Date means the required date for Substantial Completion of the Project. The Substantial Completion Date can be adjusted only by written Change Order.