Due Date for Completion definition

Due Date for Completion means the date stated in 5.1 of the Special Conditions, as may be adjusted in accordance with the Contract.
Due Date for Completion means the date specified in clause 2 of the Special Conditions of Contract, subject to adjustment due to any Variation or matters outside of the parties control.
Due Date for Completion means the date on the last day of the Time for Completion or any extension thereto of the whole of the Works or any Section thereof.

Examples of Due Date for Completion in a sentence

  • The Contractor must achieve Practical Completion by the Due Date for Completion.

  • The Contractor will not be entitled to any adjustment to the Contract Price or the Due Date for Completion unless and to the extent the Engineer issues an order in writing instructing a Variation.

  • From time to time the Principal’s Representative may require the Contractor to amend its programme to take account of the actual progress of the Works so as to achieve completion by the Due Date for Completion or as soon as reasonably practicable thereafter.

  • The Programme shall demonstrate how the Contractor proposes to meet the Due Date for Completion.

  • The sum stated as liquidated damages under the Special Conditions must be paid by the Contractor to the Principal for the period between the Due Date for Completion and the actual date of Practical Completion.

  • TIME FOR COMPLETION Due Date for Completion: The Contractor must achieve Practical Completion by the Due Date for Completion.

  • If any event or circumstance occurs which the Supplier considers may render it unable to meet any Milestone or the Due Date for Completion, it must notify the RTA’s Representative as soon as practicable and may request an extension of time.

  • Following the Contractor’s response, the parties must agree in writing on the Variation(s) to the Project, any change in the Due Date for Completion and the Contract Price or proposed charges (as the case may be).

  • Upon receipt of a Variation Request under clause 6.1, the Contractor will respond to the Principal as soon as reasonably practicable but no later than five (5) Working Days and advise the Principal of any resulting change in the Due Date for Completion and the Contract Price where possible or where this is not possible the proposed charges on a time attendance basis.

Related to Due Date for Completion

  • Date for Completion means the date for Completion specified in the Contract Specifics.

  • Time for Completion means the time for completing the Works as stated in the Contract Data (or as extended under Sub-Clause 7.3), calculated from the Commencement Date.

  • Time(s) for Completion means the time(s) stated in Schedule E by which the Supply or any particular Supply or part thereof must be completed, as such time(s) may be adjusted (including in relation to a particular instance of Supply), strictly in accordance with this Agreement;

  • Time of Completion means the time for completing the execution of and passing the Tests on Completion of the Works of any section or part thereof as stated in the Contract (or as extended under Clause...) calculated from the Commencement Date

  • Final Completion means acceptance of the Work by the County as evidenced by its signature upon Final Certificate of Completion and approval thereof by the Board of County Commissioners. The Final Certificate of Completion shall be signed only after the County has assured itself by tests, inspection or otherwise that all of the provisions of the Contract have been carried out to its satisfaction.