Initial Operation Date definition

Initial Operation Date means the date on which operation of the Project begins for the purposes for which it was planned, designed and constructed.
Initial Operation Date has the meaning set forth in Section 2.03(b).
Initial Operation Date means the date on which Initial Operation is achieved.

Examples of Initial Operation Date in a sentence

  • The amended Energy Price shall be calculated based upon the Benchmark Bid Price set forth in Table A of Exhibit L for the calendar year in which the Initial Operation Date of the Generating Facility occurs, and such Benchmark Bid Price shall then be multiplied by the Energy Price Adjustment as provided in Section 3(d) of the Final Notice to Proceed for the Generating Facility, attached hereto as Exhibit B, subject to Sections 1.02(d) and 1.02(e).

  • The Firm Operation Date shall be the date that is six (6) months after the Initial Operation Date, plus any additional days for Force Majeure as provided in Section 5.04, or as may be agreed to in a writing signed by both Parties.

  • The Expected Initial Operation Date shall be the Expected Initial Operation Date as provided in Section 2(d) of the Final Notice to Proceed for the Generating Facility, attached hereto as Exhibit B, as it may be extended pursuant to the terms of this Power Purchase Agreement.

  • Commencing on the Initial Operation Date and continuing throughout the Facility Term, Seller shall prepare and provide to SCE a Lost Output Report by the tenth (10th) Business Day following the end of each month in accordance with Exhibit M.

  • Seller shall provide at least three (3) Business Days advance Notice to SCE of the Initial Operation Date.


More Definitions of Initial Operation Date

Initial Operation Date. Defined in Subsection 4.3, Start Date.
Initial Operation Date means the date upon which the Facility first begins to process Crude Oil pursuant to the Joint Marketing Agreement.
Initial Operation Date means the date on which the Contractor demonstrates that the Facility has sustained 70% of the steam turbine generator MCR and full Emissions Compliance for a period of 120 consecutive hours;
Initial Operation Date means the date on which the Operator demonstrates that the Utility Plant has sustained 70% of the MCR and full emissions compliance for a period of 120 consecutive hours;
Initial Operation Date means the date that the Generating Facility starts producing and delivering the Contract Capacity to the Delivery Point.
Initial Operation Date means the date selected by Seller to begin Forecasting and delivering the Power Product to Buyer.
Initial Operation Date. Means the date upon which Test Energy deliveries begin.