Milestone Completion Dates definition
Examples of Milestone Completion Dates in a sentence
One such Milestone is the final approval by both parties of a more detailed project timetable (the “Project Schedule”) setting forth in more detail Milestones and Milestone Completion Dates, including all design, development and other Milestones to be achieved.
Such Project Schedule shall specify any tasks, obligations, or responsibilities (each a “Buyer Obligation”) which Buyer must perform or fulfill in order for Seller to achieve the Milestone Completion Dates for each Milestone, and the date by which Buyer is to fulfill each and every Buyer Obligation.
Upon such mutual agreement, Gatherer shall commence and acquire the necessary rights-of-way and permits, and execute until complete, construction for such Additional Services or Additional Interconnections, including following the procedures for failure to meet the Milestone Completion Dates as provided for in Section 5.3.
Notwithstanding the foregoing, the waiver of the Pressure Requirements will not otherwise relieve the Parties of the obligations under this Agreement, including, without limitation, the obligation to meet the Gathering System Completion Date or the Milestone Completion Dates.
PacifiCorp’s Representative may request that the Critical Milestones and associated Critical Milestone Completion Dates are not different from the Critical Milestones and Critical Milestone Completion Dates set forth in Appendix M.
Attached hereto as Appendix B is a preliminary project schedule setting forth the major tasks that must be completed by Developer (each a “Milestone”) and completion dates for such tasks (“Milestone Completion Dates”) as provided by Developer in accordance with the Technical Specification, including the Critical Milestones and associated Critical Milestone Completion Dates which will be consistent with Appendix M.
The preliminary project schedule shall include a Milestone (and a corresponding Milestone Completion Date) for development of a final project schedule (the “Project Schedule”) setting forth in more detail the Milestones and Milestone Completion Dates, including the Critical Milestones and Critical Milestone Completion Dates.
The Project Schedule shall specify any tasks, obligations, or responsibilities under this Agreement (each a “PacifiCorp Obligation”) which PacifiCorp must perform or fulfill in order for Developer to achieve the Milestone Completion Dates for each Milestone, and the date by which PacifiCorp is required to fulfill each and every PacifiCorp Obligation in accordance with this Agreement.
Subcontractor acknowledges that time is critically important in performing the Work and warrants that it shall meet the Milestone Completion Dates and the Completion Date.
Such Construction plans for Expansion Capacity or new facilities shall also have mutually agreeable Milestone Completion Dates similar to those described in Section 5.2 above, and the remedies under Sections 5.3 and 11 (b) shall apply, as applicable, to such Expansions or new facilities.