Project Baseline Schedule definition
Examples of Project Baseline Schedule in a sentence
All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines.
All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates or Completion Deadlines.
All Float contained in the Project Schedule, as shown in the Preliminary Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines.
The Parties shall use the Project Baseline Schedule for planning and monitoring the progress of the Design Work and Construction Work.
Developer shall submit a single hardcopy of the Project Baseline Schedule on full-size (24” x 36”) color plot sheets, along with an electronic version of the schedule in its native format.
The Project Baseline Schedule shall include the Baseline Substantial Completion Date set forth in the Preliminary Project Baseline Schedule.
Developer shall use the preliminary Project Schedule submitted with the Proposal as a foundation to prepare a Project Baseline Schedule and shall submit a draft of the Project Baseline Schedule to TxDOT for review and approval.
Approval of the Project Baseline Schedule shall be a condition of Project NTP2.
Developer shall not commence any Work pertaining to the Option Work other than the preliminary Work described above until the revised WBS and update to the Project Baseline Schedule are approved by TxDOT.
Proposer’s Preliminary Project Baseline Schedule submission shall not limit, modify or alter TxDOT’s ability to review and approve the Preliminary Project Baseline Schedule, and selection of a Proposer shall not be deemed to be acceptance or approval of Proposer’s Preliminary Project Baseline Schedule.