Project Baseline Schedule definition

Project Baseline Schedule means the logic-based critical path schedule for all Work leading up to and including Final Acceptance for all Project Segments, as described in Section 2 of the Technical Provisions.
Project Baseline Schedule means the schedule meeting the requirements of Appendix A9 (Scheduling Procedures and Reporting Requirements) approved by Company pursuant to Section 4.3.2 (Project Baseline Schedule).
Project Baseline Schedule shall have the meaning set forth in the Project Control Requirements.

Examples of Project Baseline Schedule in a sentence

  • All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines.

  • All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates or Completion Deadlines.

  • All Float contained in the Project Schedule, as shown in the Preliminary Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines.

  • The Parties shall use the Project Baseline Schedule for planning and monitoring the progress of the Design Work and Construction Work.

  • Developer shall submit a single hardcopy of the Project Baseline Schedule on full-size (24” x 36”) color plot sheets, along with an electronic version of the schedule in its native format.

  • The Project Baseline Schedule shall include the Baseline Substantial Completion Date set forth in the Preliminary Project Baseline Schedule.

  • Developer shall use the preliminary Project Schedule submitted with the Proposal as a foundation to prepare a Project Baseline Schedule and shall submit a draft of the Project Baseline Schedule to TxDOT for review and approval.

  • Approval of the Project Baseline Schedule shall be a condition of Project NTP2.

  • Developer shall not commence any Work pertaining to the Option Work other than the preliminary Work described above until the revised WBS and update to the Project Baseline Schedule are approved by TxDOT.

  • Proposer’s Preliminary Project Baseline Schedule submission shall not limit, modify or alter TxDOT’s ability to review and approve the Preliminary Project Baseline Schedule, and selection of a Proposer shall not be deemed to be acceptance or approval of Proposer’s Preliminary Project Baseline Schedule.


More Definitions of Project Baseline Schedule

Project Baseline Schedule means the approved critical path schedule prepared by the Design-Builder for performance of all Work.
Project Baseline Schedule means the logic-based critical path schedule for all Work from commencement of the Work leading up to and including, without limitation, each Milestone Schedule Deadline, Substantial Completion and Final Acceptance, to be prepared by Design- Build Team consistent with and taking into account the Milestone Schedule, as and to the extent such schedule has been approved by GDOT, all as more particularly described in Section 2.3 of the Technical Provisions, and all revisions to such schedule as provided in the DB Documents. The Project Baseline Schedule shall not mean the Project Status Schedule Updates as set forth in Section 2.3.4 of the Technical Provisions, nor shall such Project Status Schedule Updates constitute revisions or amendments to the Project Baseline Schedule.
Project Baseline Schedule means the approved critical path schedule prepared by the Design-Build Entity for performance of all Work within the Contract Time, as approved by the Owner.

Related to Project Baseline Schedule

  • Project Schedule means a document that, with respect to each Phase of the Project, identifies, coordinates and integrates the anticipated design and construction schedules, the Contracting Authority’s and Owner's responsibilities, government authority reviews and other activities as are necessary for the timely completion of the Work.

  • BASE budget means the minimum general fund budget of a district, which includes 80% of the basic

  • Contract Schedule means a schedule to this Contract;

  • Milestone Schedule means Seller’s milestone schedule, the form of which is attached to this Agreement as Exhibit Q.

  • Development Schedule shall have the meaning set forth in Section 1.1.