Ready for Startup Test Date definition
Examples of Ready for Startup Test Date in a sentence
In the event that there has been a delay in conducting the Startup Test due to a delay caused by Owner or its Personnel or resulting from an Uncontrollable Circumstance, then the Ready for Performance Test Date shall be [**] after the Ready for Startup Test Date [**].
If delays for which Contractor is not responsible delay any Start-up Test by more than [***] from the Ready for Start-up Test Date, the Work shall be deemed to have been suspended on the date that such [***] period expires as if Owner had directed such suspension in accordance with Section 22.1(a).
If such delays continue for an additional [***] after the Ready for Start-up Test Date, then, 1) Contractor shall be entitled to receive payments under the Milestone Payment Schedule for those Milestone and Progress Payments that would have come due through Substantial Completion, 2) Contractor’s obligations with respect to the Guaranteed Substantial Completion Date shall have been met, and 3) the commencement of the Warranty Periods associated with Substantial Completion shall begin.
In the event that there has been a delay in conducting the Start-up Test due to a delay caused by Owners or their Personnel or resulting from an Uncontrollable Circumstance, then the Ready for Performance Test Date shall be [***] after the Ready for Start-up Test Date [***].
Owner is responsible for conducting the Start-up Tests in accordance with the Project Schedule after all requirements for Ready for Start-up Test Date have been satisfied.
However, if the Ready for Performance Test Date has not occurred by the date [***] after the Ready for Start-up Test Date, because of delays not caused by or otherwise attributable to Contractor, then the date [***] after the Ready for Start-up Test Date shall for all purposes of this Agreement be the Ready for Performance Test Date.
In the event that there has been a delay in conducting the Start-up Test due to a delay caused by Owners or their Personnel or resulting from an Uncontrollable Circumstance, then the Ready for Performance Test Date shall be one hundred eighty (180) Days after the Ready for Start-up Test Date plus the number of Days of any delay incurred in performance of the Start-up Test that results from circumstances other than a delay caused by Owners or their Personnel or resulting from an Uncontrollable Circumstance.