Substantial Completion Guaranteed Date definition
Examples of Substantial Completion Guaranteed Date in a sentence
If the Project fails to achieve the Substantial Completion Date on or prior to close of business on the Substantial Completion Guaranteed Date, then Developer shall pay to PacifiCorp liquidated damages for each day until the Project achieves the Substantial Completion Date, in an amount equal to [ ($ )] per day for the first thirty-one (31) days following the Substantial Completion Guaranteed Date and [ (collectively, the “Delay Liquidated Damages”).
The CPM Schedule shall represent Contractor's best judgment as to how it shall complete the Work in compliance with the Schedule Milestones including the Phase Substantial Completion Guaranteed Dates, the PV Power Plant Substantial Completion Guaranteed Date, and the Final Completion Guaranteed Date.
In the event the negotiation and execution of any such Agency Subcontracts is delayed and the Project Schedule is adversely impacted (provided that Contractor is not acting in a commercially unreasonable manner), Contractor shall be entitled to a Change In Work to the extent such delay actually and demonstrably impacts the Substantial Completion Guaranteed Date for the applicable Unit or the Separated Contract Price.
On the Full Notice to Proceed Date, Contractor shall commence with the performance of the remainder of the Work in accordance with the Project Schedule and shall thereafter diligently pursue the Work assigning to it a priority as necessary for each Unit to achieve Substantial Completion on or before the Substantial Completion Guaranteed Date for such Unit.
Contractor shall prosecute the Work in accordance with the Project Schedule and shall cause Substantial Completion of the Project to occur on or before the Substantial Completion Guaranteed Date (as such date may be extended pursuant to Article 17, Article 22 or any other provision hereof).
Contractor shall cause Substantial Completion to occur on or before the Substantial Completion Guaranteed Date (as such dates may be extended pursuant to this Contract, including Articles XXIII, XVII, XXII, Section 25.01, Section 36.01 or any other provision hereof).
Approval by Owner of an Acceleration Plan shall not be deemed in any way to relieve Contractor of its obligations under this Agreement relating to the failure to achieve Substantial Completion by the Substantial Completion Guaranteed Date, shall not be a basis for an increase in the Contract Price, and shall not limit the rights of Owner under Section 15.1.
Design and prepare a written narrative description of the training program (in accordance with the provisions of Exhibit “A”) and the proposed written materials to be used in the training program, and submit such description to Owner by no later than the date that is one hundred eighty (180) days before the Substantial Completion Guaranteed Date or, if sooner, the then-anticipated Substantial Completion Date.
Owner agrees that if Contractor achieves Phase Substantial Completion for a Phase prior to with respect to ▇▇▇▇▇ ▇, ***, with respect to Phase 2 or Phase 4, ***, with respect to ▇▇▇▇▇ ▇, ***, or achieves the PV Power Plant Substantial Completion prior to the PV Power Plant Substantial Completion Guaranteed Date, Contractor shall be entitled to a bonus payment (“Bonus Payment”) from Owner in the amount of $***.
Subject to Contractor’s obligation to pay Delay Liquidated Damages to the extent set forth herein, Contractor shall have the period (the “Performance Testing Period”) through and including the ninetieth (90th) day following the Substantial Completion Guaranteed Date during which Contractor shall run, and, if necessary, re-run each of the Performance Tests necessary to demonstrate compliance with Performance Guarantees.