Acceptance of Non-Conforming Work. If the County prefers to accept Work which is not in accordance with the requirements of the Contract Documents, the County may do so instead of requiring its removal and correction, in which case the Construction Price will be reduced as appropriate and equitable. Such adjustment will be effected whether or not final payment has been made.
Appears in 2 contracts
Sources: Construction Management Agreement, Construction Management Agreement
Acceptance of Non-Conforming Work. If the County prefers to accept Work which is not in accordance with the requirements of the Contract Documents, the County may do so instead of requiring its removal and correction, in which case the Construction Price will be reduced as appropriate and equitable. Such adjustment will be effected affected whether or not final payment has been made.
Appears in 1 contract
Sources: Construction Management Agreement